Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 493.08 0 0  
1 NORTH 24 PARGANAS Resource Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building activities at South 24 Parganas and North 24 Parganas districts Under Jal Jeevan Mission (JJM) Support Activities , SM/19360 Engagement of lmplementation Support Agencies (lSAs) under JJM in the districts of the South 24 Pgs District against 10(Ten) blocks for the period of one year from 02/05/2025 to 01/05/2026. Assistant Engineer Junior Engineer ORD/000030/2025-2026 931/RS 29/04/2025 365 HARISHCHANDRAPUR PALLY UNNAYAN SAMITY 186.42 0.00 0 25
2 SOUTH 24 PARGANAS Resource Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building activities at South 24 Parganas and North 24 Parganas districts Under Jal Jeevan Mission (JJM) Support Activities , SM/19360 Engagement of lmplementation Support Agencies (lSAs) under JJM in the districts of the South 24 Pgs District against 10(Ten) blocks for the period of one year from 02/05/2025 to 01/05/2026. Assistant Engineer Junior Engineer ORD/000030/2025-2026 931/RS 29/04/2025 365 HARISHCHANDRAPUR PALLY UNNAYAN SAMITY 186.42 0.00 0 25
3 NORTH 24 PARGANAS Resource Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building activities at South 24 Parganas and North 24 Parganas districts Under Jal Jeevan Mission (JJM) Support Activities , SM/19360 Engagement of lmplementation Support Agencies (lSAs) under JJM in the districts of the South 24 Pgs District. Assistant Engineer Junior Engineer ORD/000237/2024-2025 240/RS 31/01/2025 89 HARISHCHANDRAPUR PALLY UNNAYAN SAMITY 60.12 0.00 0 99
4 SOUTH 24 PARGANAS Resource Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building activities at South 24 Parganas and North 24 Parganas districts Under Jal Jeevan Mission (JJM) Support Activities , SM/19360 Engagement of lmplementation Support Agencies (lSAs) under JJM in the districts of the South 24 Pgs District. Assistant Engineer Junior Engineer ORD/000237/2024-2025 240/RS 31/01/2025 89 HARISHCHANDRAPUR PALLY UNNAYAN SAMITY 60.12 0.00 0 99
Total 493.08 0.00 0