Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 21,740.23 4.95 0.02  
1 NORTH 24 PARGANAS Barrackpur-I North 24 Pgs W/S Division I Kaugachhi Zone-III Piped Water Supply Scheme , SM/14502 New Laying of Distribution System, Rising Main including specials, valves and pipe carrying structure, Providing FHTC including supplying, laying, fitting, fixing of 15mm NB PVC (schedule 80)/20mm OD HDPE (PE100, PN16) pipe with all necessary specials, Construction of 200 cum capacity 20 Mtr. staging height RCC Over Head Reservoir with pile foundation and pipe connection including cost of pipes & specials with soil investigation, Construction of Pump House (4.88m X 3.66m) including Sanitary Arrangement, Construction of Boundary Wall, Construction of Service Road, Improvement Of Land, Pipe carring structure for a span of 25 Meter for crossing of a Canal / River etc. for Augmentation of Ground Water Based Piped Water Supply Scheme for KAUGACHHI ZONE-III in Barrackpur-I Block of North 24 Pargana(s) District under N 24 Pgs W/S Div-I, PHE Dte. ASSISTANT ENGINEER (HQ-I) JUNIOR ENGINEER (CIVIL) ORD/000180/2023-2024 1677/NWSD-I 30/10/2023 365 NEW INDIA CONSTRUCTION 391.51 0.00 0 0
2 NORTH 24 PARGANAS Barrackpur-I North 24 Pgs W/S Division I Kaugachhi Zone-III Piped Water Supply Scheme , SM/14502 New Survey, Design Drawing & DPR Preparation for NEW PWSS (KAUGACHHI ZONE-III Water Supply Scheme) in BARRACKPUR-I BLOCK under N 24 Pgs W/S Div-I, PHE Dte. ASSISTANT ENGINEER (HQ-II) JUNIOR ENGINEER 2 ORD/000118/2022-2023 121/NWSD-I 02/02/2023 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT. LTD. 4.95 4.95 100 1
3 NORTH 24 PARGANAS Barrackpur-I North 24 Pgs W/S Division I Kaugachhi Zone-III Piped Water Supply Scheme , SM/14502 New Material Requisition To Resource Division RTOR000020/2023-2024 453/NWSD-I 26/04/2023 0 Resource Division 4.01 0.00 0 0
4 NORTH 24 PARGANAS Barrackpur-I Central Drilling Kaugachhi Zone-III Piped Water Supply Scheme , SM/14502 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 304 JHARGRAM SPV PRIVATE LIMITED 21,339.76 0.00 0 11
Total 21,740.24 4.95 0.02