Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 21,413.98 56.83 0.27  
1 NORTH 24 PARGANAS Minakhan Barasat Division Bargan Gopalpur Piped Water Supply Scheme , SM/15902 New Acceptance cum work order for Survey, Design Drawing & DPR Preparation for NEW PWSS (BARGAN GOPALPUR Water Supply Scheme) in MINAKHAN BLOCK under Barasat Division, PHE Dte. (PART-A) Assistant Engineer Junior Engineer ORD/002702/2021-2022 247/HSD 03/02/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.82 4.82 100 0
2 NORTH 24 PARGANAS Minakhan Barasat Division Bargan Gopalpur Piped Water Supply Scheme , SM/15902 New Material Requisition To Resource Division RTOR000204/2022-2023 890/BD 22/03/2023 0 Resource Division 46.13 0.00 0 0
3 NORTH 24 PARGANAS Minakhan Eastern Mechanical Bargan Gopalpur Piped Water Supply Scheme , SM/15902 New New service connection for Bargan Gopalpur PH-I, Bargan Gopalpur minakhan BILL/04047/2023-2024 BP-253-23-24 20/12/2023 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 4.97 0.00 0 0
4 NORTH 24 PARGANAS Minakhan Barasat Division Bargan Gopalpur Piped Water Supply Scheme , SM/15902 New Acceptance cum work order for Strengthening of existing concrete road for movement of rig machineries for sinking of big dia Tube well at PH No 2 within Bargan Gopalpur w/s scheme, Minakhan block under Hasnabad Sub- Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000910/2023-2024 2732/BD 07/09/2023 7 GIRIDHARI DAS 5.00 4.96 99.2 100
5 NORTH 24 PARGANAS Minakhan Barasat Division Bargan Gopalpur Piped Water Supply Scheme , SM/15902 New Acceptance cum work order for Strengthening of existing concrete road for movement of rig machineries for sinking of big dia Tube well at PH No-1 within Bargan Gopalpur w/s scheme, Minakhan block under Hasnabad Sub- Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000880/2023-2024 2715/BD 05/09/2023 10 PRITAM MUKHOPADHYAY. 8.46 8.45 99.88 100
6 NORTH 24 PARGANAS Minakhan Eastern Mechanical Bargan Gopalpur Piped Water Supply Scheme , SM/15902 New New Service Connection at PH-II under Bargan Gopalpur W/S Scheme BILL/04123/2023-2024 BP-262-23-24 02/01/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 4.84 0.00 0 0
7 NORTH 24 PARGANAS Minakhan Central Drilling Bargan Gopalpur Piped Water Supply Scheme , SM/15902 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 304 JHARGRAM SPV PRIVATE LIMITED 21,339.76 38.60 0.18 11
Total 21,413.98 56.83 0.27