Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
17 968.9 470.11 48.52  
1 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Acceptance cum work order for Sinking of 2 nos. 300 mm. x 200 mm. dia. 300 mtr deep Tubewell by D.R. Rig method with PVC pipe & strainer having 300mm dia 36 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Khulna Bhanderkhali w/s scheme (Z-I), Sandeshkhali-II block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001173/2022-2023 786/BD 13/03/2023 30 MONDAL & CO. (BASIRHAT). 47.09 37.47 79.57 0
2 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Acceptance cum work order for Sinking of 1 no. 300 mm. x 200 mm. dia. 300 mtr deep Tubewell by D.R. Rig method at PH No.-2 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Khulna Bhanderkhali w/s scheme (Z-I), Sandeshkhali-II block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer ORD/000736/2023-2024 2490/BD 18/08/2023 30 M/S DATTA ENTERPRISE. 26.91 21.67 80.53 100
3 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Material Requisition To Resource Division RTOR000256/2022-2023 923/BD 22/03/2023 0 Resource Division 94.23 0.00 0 0
4 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Formal work order for Laying of DI/UPVC distribution pipe line and providing Functional Household Tap Connection for Augmentation of Khulna Bhanderkhali W/S scheme (Zone-I), Sandeshkhali-II Block under Hasnabad Sub-Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000683/2022-2023 3182/BD 01/11/2022 90 UMWELT ENGINEER PVT.LTD. 497.55 365.15 73.39 100
5 NORTH 24 PARGANAS Eastern Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I, II and III (Zone-I)(Rep.) under Khulna-Bhanderkhali W/S Scheme District of 24 Pgs. (N) NIET No.- 26 of EE/EMD of 2022-23 (Sl. No.- 29) Assistant Engineer Junior Engineer ORD/001906/2022-2023 1170/EMD 21/03/2023 30 M.S. ENTERPRISE 39.16 35.99 91.91 90
6 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Acceptance cum work order for Dismantling & Re-construction of boundary wall for movement of rig & other machineries for sinking of big dia TW at PH no-1 in connection with Augmentation of Khulna Bhandarkhali w/s scheme (Z-I), Sandeshkhali -II block under Hasnabad Sub-Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000272/2023-2024 799/HSD 13/07/2023 10 JESMINE ENTERPRISE. 0.90 0.88 97.78 100
7 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Acceptance cum work order for Construction of approach road with cement concrete at Pump house No-1 within Khulna Bhanderkhali w/s scheme (Z-I), Sandeshkhali-II block under Hasnabad Sub-Division P.H.E. Dte Assistant Engineer Junior Engineer ORD/000274/2023-2024 801/HSD 13/07/2023 7 JESMINE ENTERPRISE. 0.57 0.51 89.47 100
8 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Acceptance cum work order for Repairing of Pump House at PH No- 1, 2 & 3 for Khulna Bhandarkhali w/s scheme (Zone-I), Sandeshkhali-II block under Hasnabad Sub-Division P.H.E. Dte. Assistant Engineer ORD/000908/2023-2024 2719/BD 05/09/2023 21 LAHIRI CONSTRUCTION. 6.11 6.01 98.36 80
9 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Acceptance cum work order for 2 nos. pump connection at PH No.-1 & 2 in connection with Augmentation for Khulna Bhanderkhali water supply scheme (Z-I) , Sandeshkhali-II block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001295/2023-2024 1417/HSD 06/11/2023 7 ANKUSH CONSTRUCTION & CO. 0.98 0.96 97.96 100
10 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Acceptance cum work order for 2 nos. pump connection at PH No.-3 in connection with Augmentation for Khulna Bhanderkhali water supply scheme (Z-I) , Sandeshkhali-II block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001913/2023-2024 285/HSD 06/03/2024 10 DEB PRASAD GHOSH. 0.67 0.67 100 100
11 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Acceptance cum work order for Dismantling & Re-construction of boundary wall for movement of rig & other machineries for sinking of big dia TW at PH no-3 in connection with Augmentation of Khulna Bhandarkhali w/s scheme (Z-I), Sandeshkhali -II block under Hasnabad Sub-Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/002346/2023-2024 800/HSD 24/05/2023 10 JESMINE ENTERPRISE. 0.84 0.80 95.24 100
12 NORTH 24 PARGANAS Eastern Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Quotation for Service Connection Charges for PH- I under Bhanderkhali W/S Scheme in the district of North 24 Pgs. JL No- 92, Plot No-1 & 65/264 BILL/04871/2023-2024 BP-320-23-24 07/03/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 8.55 0.00 0 0
13 NORTH 24 PARGANAS Eastern Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Quotation for Service Connection Charges for PH- III under Bhanderkhali W/S Scheme in the district of North 24 Pgs. JL No. 92, Plot No-112. BILL/04870/2023-2024 04/03/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 6.02 0.00 0 0
14 NORTH 24 PARGANAS Eastern Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Quotation for Service Connection Charges for PH- II under Bhanderkhali W/S Scheme in the district of North 24 Pgs. JL No- 92, Plot No- 63 BILL/04872/2023-2024 BP-327-23-24 07/03/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 18.31 0.00 0 0
15 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Enhancement of GST for the work providing FHTC for augmentation of Khulna Bhanderkhali (Zone-I) BILL/00273/2024-2025 BP-2024-25-78 10/07/2024 0 UMWELT ENGINEER PVT.LTD. 25.40 0.00 0 0
16 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Formal work order for construction of 450 cum capacity 20 mtr. staging height R.C.C. Over Head water Reservoir as per Departmental design, drawing and specification including bored pile & pile cap for Augmentation of Khulna Bhanderkhali water supply scheme (Zone - I), Sandeshkhali-II Block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000753/2023-2024 2610/BD 29/08/2023 1095 M/S PROGATI ENTERPRISE. 194.78 0.00 0 0
17 NORTH 24 PARGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Khulna Bhanderkhali Zone-I to accommodate FHTC. , SM/12735 Augmentation Acceptance cum work order for Providing Functional Household tap connection at Sitalia FP School, South Hatgacha Jr. High School, Dakshin Hatgacha Adibasi SSK and Uttar Hatgacha SSK within the command area of Khulna Bhanderkhaliw/s scheme, Sandeshkhali-II block under Hasnabad Sub- Division P.H.E. Dte. ORD/001909/2024-2025 543/HSD 10/03/2025 10 M/S RAJPATH CONSTRUCTION. 0.83 0.00 0 0
Total 968.88 470.11 48.52