| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 15 | 1,228.56 | 570.76 | 46.46 | ||||||||||||||
| 1 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Formal work order for Laying of DI rising main, DI/UPVC distribution pipe line and providing Functional Household Tap Connection in connection with Augmentation of Sahebkhali water supply scheme (Zone-II), Hingalganj Block under Hasnabad Sub-Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/000938/2022-2023 | 88/BD | 11/01/2023 | 90 | M/S NIRMAN CONSTRUCTION. | 354.45 | 323.20 | 91.18 | 1 | |
| 2 | NORTH 24 PARGANAS | Eastern Mechanical | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No. VI (New) under Sahebkhali W/S Scheme District of 24 Pgs. (N) | ORD/001286/2023-2024 | 4940/EMD | 18/08/2023 | 30 | KUNDU ELECTRICAL ENTERPRISE | 13.82 | 0.00 | 0 | 0 | |||
| 3 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Material Requisition To Resource Division | RTOR000258/2022-2023 | 920/BD | 22/03/2023 | 0 | Resource Division | 137.48 | 0.00 | 0 | 0 | |||
| 4 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Material Requisition To Resource Division | RTOR000120/2023-2024 | 4175/BD | 30/10/2023 | 0 | Resource Division | 18.56 | 0.00 | 0 | 0 | |||
| 5 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Formal work order for construction of 300 cum capacity 20 mtr. staging height R.C.C. Over Head Water Reservoir as per Departmental design, drawing and specification including bored pile & pile cap for Augmentaion of Sahebkhali water supply scheme (Zone-I), Hingalganj Block under Hasnabad Sub-Division, P.H.E. Dte. | Assistant Engineer | ORD/001266/2023-2024 | 4200/BD | 31/10/2023 | 365 | M/S RAJPATH CONSTRUCTION. | 150.42 | 0.00 | 0 | 0 | ||
| 6 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Acceptance cum work order for Sinking of 1 Nos. 330.00 mtr. Deep 100 X 50 mm. dia. Trial-cum-production Tube well fitted with Indian Mark - II pump with PVC pipe & strainers at T/W site-1 for Sahebkhali w/s scheme (Zone-II), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. | ORD/000022/2024-2025 | 629/HSD | 12/06/2024 | 10 | DEB PRASAD GHOSH. | 3.50 | 0.00 | 0 | 0 | |||
| 7 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Acceptance cum work order for Sinking of 1 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at PH No -I with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Sahebkhali w/s scheme (Z-II), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. | Assistant Engineer | ORD/000534/2024-2025 | 2900/BD | 03/10/2024 | 30 | SUBHAJIT SAHA | 31.68 | 0.00 | 0 | 0 | ||
| 8 | NORTH 24 PARGANAS | Eastern Mechanical | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I, II and III (Replacement) under Sahebkhali W/S Scheme District of 24 Pgs. (N) | Assistant Engineer | Junior Engineer | ORD/001277/2023-2024 | 4938/MD | 18/08/2023 | 30 | KARTICK BAL | 41.40 | 36.57 | 88.33 | 70 | |
| 9 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Acceptance cum work order for Sinking of 2 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at PH No.-1 & 2 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Sahebkhali w/s scheme (Zone-I), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/001683/2023-2024 | 526/BD | 20/02/2024 | 45 | UTPAL CONSTRUCTION & CO. | 61.24 | 48.73 | 79.57 | 100 | |
| 10 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Acceptance cum work order for Sinking of 3 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at PH No.-3, 4 & 5 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Sahebkhali w/s scheme (Z-I), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/001932/2023-2024 | 915/BD | 15/03/2024 | 60 | SRI KRISHNA CO-OP-LABOUR CONTRACT AND CONST SOC LTD. | 94.87 | 71.18 | 75.03 | 100 | |
| 11 | NORTH 24 PARGANAS | Eastern Mechanical | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.IV and V (Replacement) under Sahebkhali W/S Scheme District of 24 Pgs. (N) | Assistant Engineer | Junior Engineer | ORD/001278/2023-2024 | 4939/EMD | 18/08/2023 | 622 | ASHOKE ADHIKARY | 27.57 | 0.00 | 0 | 100 | |
| 12 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Formal work order for Construction of 250 cum capacity 20 mtr staging height R.C.C Over Head water Reservoir as per Departmental design, drawing and specification including bored pile & pile cap for Augmentation of Sahebkhali water supply scheme (Zone-II), Hingalganj Block under Hasnabad Sub-Division, PHE Dte. under Barasat Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/001228/2023-2024 | 4110/BD | 17/10/2023 | 791 | ROY CHOWDHURY CONSTRUCTION. | 140.37 | 91.08 | 64.89 | 75 | |
| 13 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Acceptance cum work order for Construction of switch room cum chlorine room with sanitary and water supply arrangement including plinth protection at PH No.-1 (Size-5.40x3.60 mtr.) for Augmentation of Sahebkhali w/s scheme (Z-II), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. | Assistant Engineer | ORD/001293/2024-2025 | 301/BD | 28/01/2025 | 75 | M/S S.HAQUE & CO. | 12.36 | 0.00 | 0 | 0 | ||
| 14 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Formal work order for Additional laying of UPVC distribution pipe line including protection work for DI pipe at N/H/O Provas Halder towards Suvomay Mondal house & other allied work for UPVC pipe laying at different places in connection with Augmentation of Sahebkhali w/s scheme (Z-I), Hingalganj block within Hasnabad Sub-Division under Barasat Division P.H.E. Dte. | Assistant Engineer | ORD/000069/2025-2026 | 1797/BD | 30/05/2025 | 60 | SAHA CONSTRUCTION & CO | 139.89 | 0.00 | 0 | 0 | ||
| 15 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Sahebkhali to accommodate FHTC , SM/12278 | Augmentation | Acceptance cum work order for 2 nos. pump connection at PH No.-1 & 2 in connection with Augmentation for Sahebkhali water supply scheme (Z-I) , Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/001304/2024-2025 | 150/HSD | 27/01/2025 | 10 | M/S DATTA ENTERPRISE. | 0.95 | 0.00 | 0 | 100 | |
| Total | 1,228.55 | 570.78 | 46.46 | ||||||||||||||