| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2 | 76.64 | 72.44 | 94.52 | ||||||||||||||
| 1 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Kulia to accommodate FHTC , SM/11755 | Augmentation | Acceptance cum work order for Laying of UPVC distribution main and Providing FHTC (Functional Household Tap Connection ) by augmentation for Kulia water supply scheme in Baduria block under Barasat Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/000813/2022-2023 | 3586/BD | 08/12/2022 | 30 | PREMANANDA ROY BISWAS. | 73.89 | 72.44 | 98.04 | 100 | |
| 2 | NORTH 24 PARGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Kulia to accommodate FHTC , SM/11755 | Augmentation | Material Requisition To Resource Division | RTOR000161/2022-2023 | 494/BD | 17/02/2023 | 0 | Resource Division | 2.75 | 0.00 | 0 | 0 | |||
| Total | 76.64 | 72.44 | 94.52 | ||||||||||||||