Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
6 | 333.65 | 158.25 | 47.43 | ||||||||||||||
1 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Maminpur to accommodate FHTC , SM/11665 | Augmentation | Route Survey, Design Drawing & DPR Preparation for MAMINPUR Water Supply Scheme in Basirhat-II Block under Barasat Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/002760/2021-2022 | 305/ BHTSD | 07/03/2022 | 15 | SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. | 3.15 | 2.98 | 94.6 | 1 | |
2 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Maminpur to accommodate FHTC , SM/11665 | Augmentation | Material Requisition To Resource Division | RTOR000145/2022-2023 | 3820/BD | 23/12/2022 | Resource Division | 16.81 | 0.00 | 0 | 0 | ||||
3 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Maminpur to accommodate FHTC , SM/11665 | Augmentation | Formal work order for Laying of UPVC distribution pipe line and Providing FHTC (Functional Household Tap Connection ) for augmentation of Maminpur water supply scheme in Basirhat-II block under Barasat Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/000742/2022-2023 | 3340/BD | 16/11/2022 | 90 | MONDAL PRECISION PVT.LTD | 194.77 | 155.27 | 79.72 | 83 | |
4 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Maminpur to accommodate FHTC , SM/11665 | Augmentation | Acceptance cum work order for Sinking of 2 nos. 300mm. x 200 mm. big dia 300 mtr deep Tube well by Direct Rotary Rig method for pump house no - 1 & 2 using PVC pipe & strainer having 300 mm Dia 36 mtr. long Housing Pipe and 200 mm Dia 30 mtr. long filter for Augmentation of Mominpur Water Supply Scheme in Basirhat - II Block of Basirhat Sub- Division under Barasat Division, PHE Dte. | Assistant Engineer | ORD/001151/2022-2023 | 674/BD | 01/03/2023 | 30 | DHELA BABA ENTERPRISE | 42.67 | 0.00 | 0 | 0 | ||
5 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Maminpur to accommodate FHTC , SM/11665 | Augmentation | Material Requisition To Resource Division | RTOR000157/2023-2024 | 4417/BD | 10/11/2023 | Resource Division | 11.09 | 0.00 | 0 | 0 | ||||
6 | NORTH 24 PARAGANAS | Eastern Mechanical | Augmentation of ground water based piped water supply scheme for Maminpur to accommodate FHTC , SM/11665 | Augmentation | Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I and II (Rep.) under Bansjhari-Mullickpur and Maminpur W/S Scheme with Pump House No-I under Rajnagar W/S Scheme District of 24 Pgs. (N) | Assistant Engineer | Junior Engineer | ORD/003332/2023-2024 | 4809./EMD | 09/08/2023 | 30 | S.G. ENTERPRISE | 65.16 | 0.00 | 0 | 75 | |
Total | 333.65 | 158.25 | 47.43 |