Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 330.57 235.38 71.2  
1 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Route Survey, Design Drawing & Preparation of DPR for Ramnagar Water Supply Scheme in Gaighata Block within the Jurisdiction of Bongaon Sub-Division under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001350/2021-2022 146/Bon 18/02/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 2.98 2.98 100 1
2 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Repairing & Renovation of 02No. Pump House and allied works at Ramnagar water supply scheme under Bongaon Sub-Division, P.H.E.Dte. Assistant Engineer Junior Engineer ORD/002904/2021-2022 541/BON 03/11/2021 21 MA CONSTRUCTION. 2.52 2.47 98.02 1
3 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Material Requisition To Resource Division RTOR000096/2022-2023 3663/BD 13/12/2022 Resource Division 7.98 0.00 0 0
4 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Material Requisition To Resource Division RTOR000117/2022-2023 3691/BD 14/12/2022 Resource Division 12.68 0.00 0 0
5 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Formal work order for laying of DI/UPVC distribution pipe line and Providing Functional House Hold Tap Connection (FHTC) For Augmentation of Ramnagar Water Supply Scheme under Bongaon Sub-Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000766/2022-2023 3472/BD 01/12/2022 90 SRI KRISHNA CO-OP-LABOUR CONTRACT AND CONST SOC LTD. 200.08 199.57 99.75 1
6 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Acceptance cum work order for Sinking of 1(one) no. 300mm x 200 mm. dia. Replacement of Tube well 250 mtr deep by D.R. method with UPVC pipe & UPVC ribbed strainer for Augmentation of Ramnagar water supply scheme at Head Work Site under Bongaon Sub-Division P.H.E.Dte. Assistant Engineer Junior Engineer ORD/000778/2023-2024 2685/BD 04/09/2023 30 SAHA CONSTRUCTION & CO 16.17 5.87 36.3 100
7 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Acceptance cum work order for Sinking of 1(one) no. 300mm x 200 mm. dia. Replacement of Tube well 250 mtr deep by D.R. method with UPVC pipe & UPVC ribbed strainer for Augmentation of Ramnagar water supply scheme at 2nd T/W Site under Bongaon Sub-Division P.H.E.Dte. Assistant Engineer Junior Engineer ORD/000793/2023-2024 2684/BD 04/09/2023 30 SAHA CONSTRUCTION & CO 16.17 5.61 34.69 100
8 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Acceptance cum work order for Repairing of Boundary wall at Head Work site, Construction of Boundary wall at 2nd Pump House site and Construction of Approach Road at Head Work site and 2nd T/W Site under Augmentation of Ramnagar Water Supply Scheme, Gaighata Block within the jurisdiction of Bongaon Sub-Division under Barasat Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001748/2023-2024 565/BD 22/02/2024 45 JP CONSTRUCTION & SUPPLIERS. 12.84 6.33 49.3 100
9 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Acceptance cum work order for Improvement of Iron Elimination Plant and other related allied works and Repairing & renovation of Compressor Room for Iron Elimination Plant under Augmentation of Ramnagar Water Supply Scheme, Gaighata Block within the jurisdiction of Bongaon Sub-Division under Barasat Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001786/2023-2024 630/BD 28/02/2024 45 GHOSH CONSTRUCTION 5.97 2.98 49.92 100
10 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of ground water based piped water supply scheme for Ramnagar to accommodate FHTC , SM/11603 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I & II (Zone-I)(Rep.) and Pump house no-III (New) under Dakshin Bhebia W/S Scheme with Pump House No-I and II under Ramnagar W/S scheme District of 24 Pgs. (N) Assistant Engineer Junior Engineer ORD/001158/2023-2024 4808/EMD 09/08/2023 30 A.G ENTERPRISE. 53.18 9.57 18 40
Total 330.57 235.37 71.2