Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 186.79 144.05 77.12  
1 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Bergum Piped Water Supply Scheme at Habra-I Block (Phase-I) , SM/08775 Retrofitting Acceptance cum work order for Route Survey, Design Drawing & DPR Preparation for Chaital Water Supply Scheme under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000967/2021-2022 2164/HSD 28/12/2021 21 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.49 4.48 99.78 1
2 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Bergum Piped Water Supply Scheme at Habra-I Block (Phase-I) , SM/08775 Retrofitting Acceptance cum work order for Providing Functional House Hold Tap Connection (FHTC) from existing distribution system at Bergum Water Supply Scheme within the jurisdiction of Habra Sub-Division under Barasat Division, P.H.E. Dte.( For balance work of Retrofitting). Assistant Engineer Junior Engineer ORD/000837/2022-2023 3582/ BD 08/12/2022 30 ANKUSH CONSTRUCTION & CO. 16.19 15.18 93.76 1
3 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Bergum Piped Water Supply Scheme at Habra-I Block (Phase-I) , SM/08775 Retrofitting Continuation work order for Hiring Diesel Luxury Car on Daily basis (for 6 months from 01.04.2023 to 30.06.2023) for the office use of the Executive Engineer, Barasat Division, PHE Dte Assistant Engineer ORD/001306/2022-2023 1044/BD 31/03/2023 91 MADHAB CHANDRA DAS 0.45 0.69 153.33 100
4 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Bergum Piped Water Supply Scheme at Habra-I Block (Phase-I) , SM/08775 Retrofitting Material Requisition To Resource Division RTOR000015/2021-2022 250/BD 27/01/2022 0 Resource Division 1.99 0.00 0 0
5 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Bergum Piped Water Supply Scheme at Habra-I Block (Phase-I) , SM/08775 Retrofitting Formal Work Order for Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and Jal Swapna) under command area of Bergum Water Supply Scheme at Habra-I Block within the jurisdiction of Habra Sub-Division, under Barasat Division, PHE Dte. (Phase-I). Assistant Engineer Junior Engineer ORD/000864/2021-2022 2484/BD 17/12/2021 1890 UNICON INDIA. 163.67 123.70 75.58 100
Total 186.79 144.05 77.12