Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 108.62 68.12 62.71  
1 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Sadiknagar Zone-II Water Supply Scheme at Basirhat-II Block, Dist.-North 24 Parganas (Phase-I) , SM/07617 Retrofitting Formal work order for "Providing Functional Household Tap Connection (FHTC) from existing and new proposed distribution system within the command area Malatipur & Chaita (Part) Mouzas under Sadiknagar Zone - II Water Supply Scheme at Basirhat - II Block Under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001760/2020-2021 495/BD. 26/02/2021 90 ORIENT CONSTRUCTION. 97.09 56.62 58.32 1
2 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Sadiknagar Zone-II Water Supply Scheme at Basirhat-II Block, Dist.-North 24 Parganas (Phase-I) , SM/07617 Retrofitting Route Survey, Design Drawing & DPR Preparation for SADIKNAGAR-II Water Supply Scheme in Basirhat-II Block under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001951/2021-2022 207/BHTSD 28/02/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 3.51 3.50 99.72 1
3 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Sadiknagar Zone-II Water Supply Scheme at Basirhat-II Block, Dist.-North 24 Parganas (Phase-I) , SM/07617 Retrofitting Acceptance cum work order for Route Survey, Design Drawing & DPR Preparation for Khulna Bhandarkhali Zone-I Water Supply Scheme under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/002035/2021-2022 2177/HSD 28/12/2021 21 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 3.92 3.93 100.26 1
4 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Sadiknagar Zone-II Water Supply Scheme at Basirhat-II Block, Dist.-North 24 Parganas (Phase-I) , SM/07617 Retrofitting Route Survey, Design Drawing & DPR Preparation for Krishnachandrapur Water Supply Scheme under Bongaon Sub-Division, under Barasat Division, PHE.Dte. Assistant Engineer Junior Engineer ORD/001118/2021-2022 612/Bon 31/12/2021 20 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.09 4.07 99.51 1
5 NORTH 24 PARGANAS Barasat Division Providing Functional Household Tap Connection (FHTC) in connection with Jal Jivan Mission (JJM and Jal Swapna) under command area of Sadiknagar Zone-II Water Supply Scheme at Basirhat-II Block, Dist.-North 24 Parganas (Phase-I) , SM/07617 Retrofitting Material Requisition To Resource Division RTOR000076/2022-2023 2988/BD 29/09/2022 0 Resource Division 0.01 0.00 0 0
Total 108.62 68.12 62.71