Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
3 | 8.54 | 0 | 0 | ||||||||||||||
1 | NADIA | Nadia Arsenic Civil Division II | Retrofitting of Bahirgachi Zone-I water supply scheme underChapra Block by providing Functional House Tap Conectionunder Jal Sapno Mission in Nadia District , SM/08305 | Retrofitting | QUOTATION FOR NISCHINTAPUR WATER SUPPLY SCHEME | VCH/000291/2021-2022 | null | 28/09/2021 | WEST BENGAL STATE ELECTRICTY DISTRIBUTION COMPANY LTD. | 1.78 | 0.00 | 0 | 0 | ||||
2 | NADIA | Nadia Arsenic Civil Division II | Retrofitting of Bahirgachi Zone-I water supply scheme underChapra Block by providing Functional House Tap Conectionunder Jal Sapno Mission in Nadia District , SM/08305 | Retrofitting | Quotation for Nischintapur W/S scheme | VCH/000899/2020-2021 | null | 28/09/2020 | WEST BENGAL STATE ELECTRICTY DISTRIBUTION COMPANY LTD. | 1.78 | 0.00 | 0 | 0 | ||||
3 | NADIA | Nadia Arsenic Civil Division II | Retrofitting of Bahirgachi Zone-I water supply scheme underChapra Block by providing Functional House Tap Conectionunder Jal Sapno Mission in Nadia District , SM/08305 | Retrofitting | Providing Functional House Hold Tap Connection (FHTC) including supply of 15 mm dia GI/PVC pipe of average length of 15 mtr, 10 mm dia gun-Metal ferrule, Saddle piece (As required size), 15 mm dia Bib cock etc all complete at Bahirgachhi Zone-I (Vill- Bahirgachhi) W/s Scheme in Nadia District under Nadia Arsenic Civil Division-II, P.H.E. Dte. | Assistant Engineer -I (HQ), Nadia Arsenic Civil Divisio | ORD/000039/2020-2021 | 1186/NACD-II | 13/11/2020 | 25 | ST. ANTHONY ENTERPRISE | 4.98 | 0.00 | 0 | 0 | ||
Total | 8.55 | 0.00 | 0 |