Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 469.51 331.8 70.67  
1 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Distribution Design for preparation of DPR for providing FHTC (Functional Household Tap Connection) by retrofitting under Jal Swapna for Duttapulia Zone - II Water Supply Scheme in Ranaghat-II Block of Nadia District under Nadia Arsenic Division-I, P.H.E. Dte. Assistant Engineer-II Junior Engineer-III ORD/000226/2021-2022 71/AE-II/NAD-I 24/02/2022 30 UMWELT ENGINEER PVT. LTD. 4.80 4.80 100 100
2 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Route Survey for preparation of DPR for providing FHTC (Functional Household Tap Connection) by retrofitting under Jal Swapna for Duttapulia Zone - II Water Supply Scheme in Ranaghat-II Block of Nadia District under Nadia Arsenic Division-I, P.H.E. Dte. Assistant Engineer-II Junior Engineer-III ORD/000225/2021-2022 70/AE-II/NAD-I 24/02/2022 30 UMWELT ENGINEER PVT. LTD. 4.67 4.67 100 100
3 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Collection of Household data through mobile app for FHTC Connection at following schemes under Nadia Arsenic Division-I PHE Dte. Schemes:- i)Matikumra ii)Duttaphulia Zone-I iii)Duttaphulia Zone-II Assistant Engineer-I ,Assistant Engineer-II Junior Engineer-I,Junior Engineer-III ORD/000004/2023-2024 166/AE-I/NAD-I 12/04/2023 15 TECH VISION 4.84 4.84 100 40
4 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Retrofitting work at Duttaphulia Mouza inconnection with Augmentation to accomodate FHTC under JJM for Duttaphulia Zone- II Ground water based piped watrer supply scheme ( Phase- I ) Block- Ranaghat -II Dist- Nadia under Nadia Arsenic Division-I , P.H.E Dte.(Sl.No. 08)" Assistant Engineer-II Junior Engineer-IV ORD/000078/2023-2024 1384/NAD-I 16/05/2023 30 MESSRS FREEDOM CONSTRUCTION 72.08 71.49 99.18 100
5 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Renovation of I E P (225m3/hr.) at Duttaphulia Zone II W/S Scheme under Nadia Arsenic Division - I , PHE Dte. Assistant Engineer-II Junior Engineer-IV ORD/000230/2023-2024 2299/NAD-I 29/09/2023 15 SATYABRATA CHAKRABORTY 19.29 0.00 0 0
6 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Material Requisition To Resource Division RTOR000007/2022-2023 1781/NAD-I 22/09/2022 Resource Division 20.94 0.00 0 0
7 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Material Requisition To Resource Division RTOR000030/2023-2024 68/NAD-I 16/01/2024 Resource Division 3.72 0.00 0 0
8 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Providing FHTC (Functional Household Tap Connection) under Jaldhara/Jal Swapna for Duttaphulia Zone-II (Part-I) at Ranaghat-II Block by Augmentation of Ground Water based PWSS for Duttaphulia Zone-I Water SUpply Scheme under Nadia Arsenic Division-I, P.H.E Dte. Assistant Engineer-II Junior Engineer-III,Junior Engineer-IV ORD/000030/2022-2023 1463/NAD-I 18/08/2022 90 APURBA MANDAL 321.95 236.16 73.35 85
9 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Construction and installation of MANIFOLD and allied works at OHR site under Duttaphulia Zone-II Ground Based Water Supply Scheme under Ranaghat-II under Nadia Arsenic Division-I,P.H.E Dte. in connection with providing FHTC for Duttaphulia Zone-II (Phase-I) under JJM (Sl.no.09) Assistant Engineer-II Junior Engineer-IV ORD/000037/2023-2024 1362 / NAD-I 12/05/2023 15 DULAL MAJUMDER 13.03 9.84 75.52 100
10 NADIA Nadia Arsenic Division I Augmentation to accommodate FHTC for Duttapulia Zone-II Ground Water Based Piped Water Supply Scheme (Phase-I), Block-Ranaghat-II, District-Nadia. , SM/10659 Augmentation Restoration of damages pipelines from Duttaphulia more to BSF camp in Ranaghat- II, Block under Nadia Arsenic Division-I,PHE Dte. Assistant Engineer-II Junior Engineer-IV ORD/000004/2024-2025 142/AE-II/NAD-I 07/06/2024 30 BUDDHADEV MONDAL 4.19 0.00 0 100
Total 469.51 331.80 70.67