Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 3,968.22 316.21 7.97  
1 NADIA Nadia Division SURFACE WATER BASED W/S SCHEME FOR ARSENIC AFFECTED AREAS OF NADIA DISTRICT ZONE IX/A (NORTHERN SECTOR PART-II) TO ACCOMMODATE FHTC UNDER NADIA DIVISION , SM/11652 Augmentation Route Survey, Design Drawing & DPR Preparation for ZONE 9/A of Surface Water based Piped water Supply Scheme for Northern Sector Part-II in Nakashipara Block under Debagram Sub Division, PHE Dte. Assistant Engineer ORD/000807/2021-2022 157/DSD 17/03/2022 30 SRIJAN ECOLOGICAL UPLIFTMENT PVT. LTD 4.66 4.63 99.36 100
2 NADIA Nadia Division SURFACE WATER BASED W/S SCHEME FOR ARSENIC AFFECTED AREAS OF NADIA DISTRICT ZONE IX/A (NORTHERN SECTOR PART-II) TO ACCOMMODATE FHTC UNDER NADIA DIVISION , SM/11652 Augmentation Repair and renovation works of R.C.C. Elevated Reservoir 700 cum. for Providing FHTC (Functional Household Tap Connection) for Zone IX/A Water Supply Scheme in Nakashipara Block of Nadia District under Nadia Division, PHE Dte. Assistant Engineer Junior Engineer 2 ORD/000258/2023-2024 4007/ND 07/09/2023 60 CHANDAN ROY 27.44 9.67 35.24 37
3 NADIA Nadia Division SURFACE WATER BASED W/S SCHEME FOR ARSENIC AFFECTED AREAS OF NADIA DISTRICT ZONE IX/A (NORTHERN SECTOR PART-II) TO ACCOMMODATE FHTC UNDER NADIA DIVISION , SM/11652 Augmentation Installation of Har Ghar Jal (HGJ) Display Board at different Villages under various PWSS under Nadia Division, P.H.E. Dte. Assistant Engineer Junior Engineer 2 ORD/000419/2023-2024 5349/ND 01/12/2023 60 IMAGIN 96.97 1.40 1.44 40
4 NADIA Nadia Division SURFACE WATER BASED W/S SCHEME FOR ARSENIC AFFECTED AREAS OF NADIA DISTRICT ZONE IX/A (NORTHERN SECTOR PART-II) TO ACCOMMODATE FHTC UNDER NADIA DIVISION , SM/11652 Augmentation Material Requisition To Resource Division RTOR000134/2023-2024 248/ND 11/01/2024 0 Resource Division 7.22 0.00 0 0
5 NADIA Nadia Division SURFACE WATER BASED W/S SCHEME FOR ARSENIC AFFECTED AREAS OF NADIA DISTRICT ZONE IX/A (NORTHERN SECTOR PART-II) TO ACCOMMODATE FHTC UNDER NADIA DIVISION , SM/11652 Augmentation Restoration of Bholadanga welcome gate to Bangoria over Bridge via NH 34 BILL/00511/2024-2025 302/PFMS 02/10/2024 0 EXECUTIVE ENGINEER, WBSRDA NADIA DIVISION 20.27 0.00 0 0
6 NADIA Nadia Division SURFACE WATER BASED W/S SCHEME FOR ARSENIC AFFECTED AREAS OF NADIA DISTRICT ZONE IX/A (NORTHERN SECTOR PART-II) TO ACCOMMODATE FHTC UNDER NADIA DIVISION , SM/11652 Augmentation Providing FHTC, Supplying, laying of distribution system including with all necessary specials, valves, UPVC/HDPE Pipes, 10 mm gun metal ferrule, saddle piece etc. & Construction of Manifold all complete for Zone- III/A, III/B, VIII/A, VIII/B, VIII/C, IX/A & IX/B (Northern Sector Part-II) Under Nakashipara Block of Nadia District. Assistant Engineer Junior Engineer 2 ORD/000355/2023-2024 4588/ND 06/10/2023 721 SRIJAN ECOLOGICAL UPLIFTMENT PVT. LTD 2,304.90 300.51 13.04 19
7 NADIA Nadia Division SURFACE WATER BASED W/S SCHEME FOR ARSENIC AFFECTED AREAS OF NADIA DISTRICT ZONE IX/A (NORTHERN SECTOR PART-II) TO ACCOMMODATE FHTC UNDER NADIA DIVISION , SM/11652 Augmentation Additional Work for Augmentation of Surface Water Based Piped Water Supply Scheme for Different Zones (Northern Sector Part-I) , ZONE V / A (Northern Sector Part-I) in Kaliganj Block & Different Zones (Northern Sector Part-II) in Nakashipara Block of Nadia District under Nadia Division, PHE Dte. Assistant Engineer Junior Engineer 1 ORD/000232/2024-2025 6464/ND 01/10/2024 365 UMWELT ENGINEER PVT LTD 1,506.76 0.00 0 52
Total 3,968.22 316.20 7.97