| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6 | 223.72 | 185.98 | 83.13 | ||||||||||||||
| 1 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-VI within Kaliganj Block. (Phase-C) , SM/08961 | Retrofitting | Laying additional distribution pipeline for providing FHTC at Sherpur Village zone-VI Phase- C, Part- I , Surface water based Water Supply Scheme, Nadia Northern Sector , Kaliganj Block. | Assistant Engineer | ORD/000060/2022-2023 | 175/A/DSD | 18/04/2022 | 30 | BALAJEE ENTERPRISE | 1.54 | 1.52 | 98.7 | 100 | ||
| 2 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-VI within Kaliganj Block. (Phase-C) , SM/08961 | Retrofitting | Laying additional distribution pipeline for providing FHTC at zone-VI Phase- C, Part- I , Surface water based Water Supply Scheme, Nadia Northern Sector , Kaliganj Block. | Assistant Engineer | ORD/000816/2021-2022 | 48/DSD | 07/02/2022 | 15 | BALAJEE ENTERPRISE | 4.95 | 4.93 | 99.6 | 100 | ||
| 3 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-VI within Kaliganj Block. (Phase-C) , SM/08961 | Retrofitting | Providing Functional Household Tap Connection (FHTC) at Surface Water Based Water Supply Scheme (Northern Sector) Part-I, Zone-VI within Kaliganj Block(Phase-C) | Assistant Engineer | Junior Engineer 3 | ORD/000356/2021-2022 | 7058/ND | 06/12/2021 | 90 | BALAJEE ENTERPRISE | 176.90 | 169.22 | 95.66 | 0 | |
| 4 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-VI within Kaliganj Block. (Phase-C) , SM/08961 | Retrofitting | Material Requisition To Resource Division | RTOR000039/2021-2022 | 429/ND | 31/01/2022 | 0 | Resource Division | 1.99 | 0.00 | 0 | 0 | |||
| 5 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-VI within Kaliganj Block. (Phase-C) , SM/08961 | Retrofitting | Material Requisition To Resource Division | RTOR000082/2022-2023 | 4309/ND | 29/09/2022 | 0 | Resource Division | 24.88 | 0.00 | 0 | 0 | |||
| 6 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-VI within Kaliganj Block. (Phase-C) , SM/08961 | Retrofitting | Filling fine sand over upvc pipeline for road restoration work at nimtala juranpur road(both side of road) in connection with augmentation of surface water based w/s scheme for Arsenic affected areas of Nadia district( Northern sector part-I) under Nadia Division PHE Dte. | Assistant Engineer | Junior Engineer 1 | ORD/000003/2024-2025 | 918KlySD-I | 07/06/2024 | 15 | UMWELT ENGINEER PVT LTD | 13.46 | 10.31 | 76.6 | 100 | |
| Total | 223.72 | 185.99 | 83.14 | ||||||||||||||