| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 7 | 253.48 | 171.16 | 67.52 | ||||||||||||||
| 1 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-III and IX within Kaliganj Block.(Phase-D) , SM/08957 | Retrofitting | Providing Functional Household Tap Connection(FHTC) at Surface Water Based Water Supply Scheme (Northern Sector) Part-I, Zone-III & IX within KALIGANJ BLOCK(Phase-D). | Assistant Engineer | Junior Engineer 3 | ORD/000325/2021-2022 | 7052/ND | 06/12/2021 | 90 | TARUN KUMAR BHATTACHARYA | 180.22 | 168.03 | 93.24 | 0 | |
| 2 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-III and IX within Kaliganj Block.(Phase-D) , SM/08957 | Retrofitting | Material Requisition To Resource Division | RTOR000065/2021-2022 | 796/ND | 18/02/2022 | 0 | Resource Division | 16.50 | 0.00 | 0 | 0 | |||
| 3 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-III and IX within Kaliganj Block.(Phase-D) , SM/08957 | Retrofitting | Filling fine sand over upvc pipeline for road restoration work at nimtala juranpur road(both side of road) in connection with augmentation of surface water based w/s scheme for Arsenic affected areas of Nadia district( Northern sector part-I) under Nadia Division PHE Dte. | Assistant Engineer | Junior Engineer 1 | ORD/000003/2024-2025 | 918KlySD-I | 07/06/2024 | 15 | UMWELT ENGINEER PVT LTD | 13.46 | 3.13 | 23.25 | 100 | |
| 4 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-III and IX within Kaliganj Block.(Phase-D) , SM/08957 | Retrofitting | Material Requisition To Resource Division | RTOR000181/2023-2024 | 316/ND | 15/01/2024 | 0 | Resource Division | 7.11 | 0.00 | 0 | 0 | |||
| 5 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-III and IX within Kaliganj Block.(Phase-D) , SM/08957 | Retrofitting | Material Requisition To Resource Division | RTOR000182/2023-2024 | 317/ND | 15/01/2024 | 0 | Resource Division | 8.18 | 0.00 | 0 | 0 | |||
| 6 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-III and IX within Kaliganj Block.(Phase-D) , SM/08957 | Retrofitting | Material Requisition To Resource Division | RTOR000180/2023-2024 | 315/ND | 15/01/2024 | 0 | Resource Division | 16.25 | 0.00 | 0 | 0 | |||
| 7 | NADIA | Nadia Division | Providing FHTC Surface Water Based Water Supply Scheme(Northern Sector), Part-I, Zone-III and IX within Kaliganj Block.(Phase-D) , SM/08957 | Retrofitting | Material Requisition To Resource Division | RTOR000179/2023-2024 | 314/ND | 15/01/2024 | 0 | Resource Division | 11.76 | 0.00 | 0 | 0 | |||
| Total | 253.48 | 171.16 | 67.52 | ||||||||||||||