| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 5 | 107.01 | 70.4 | 65.79 | ||||||||||||||
| 1 | NADIA | Nadia Division | Providing Functional House Tap Connection from Teinpur Zone-III Water Supply Scheme (Phase-I) of Retrofitting under Jal Swapna Program in Nadia District under Nadia Division, P.H.E Dte. , SM/08663 | Retrofitting | Providing Functional House Tap Connection from Teinpur Zone-III Water Supply Scheme (Phase-I) of Retrofitting under Jal Swapna Program in Nadia District under Nadia Division, P.H.E Dte. | VCH/001014/2021-2022 | 606/PFMS | 11/03/2022 | 0 | OTHERS | 8.14 | 0.00 | 0 | 0 | |||
| 2 | NADIA | Nadia Division | Providing Functional House Tap Connection from Teinpur Zone-III Water Supply Scheme (Phase-I) of Retrofitting under Jal Swapna Program in Nadia District under Nadia Division, P.H.E Dte. , SM/08663 | Retrofitting | Hiring of Diesel car for official use in the office of the Assistant Engineer, Ranaghat Sub-Division, P.H. E. Dte., Kalyani, Nadia. Period of work 01-02-2023 to 31-07-2023= 183 days. | Assistant Engineer | ORD/000512/2022-2023 | 92/RSD | 01/02/2023 | 183 | SUMAN CHAKRABORTY, A-7/40, KALYANI, NADIA | 3.20 | 0.66 | 20.63 | 25 | ||
| 3 | NADIA | Nadia Division | Providing Functional House Tap Connection from Teinpur Zone-III Water Supply Scheme (Phase-I) of Retrofitting under Jal Swapna Program in Nadia District under Nadia Division, P.H.E Dte. , SM/08663 | Retrofitting | Hiring of Diesel car for official use in the office of the Assistant Engineer, Ranaghat Sub-Division, P.H. E. Dte., Kalyani, Nadia. Period of work 11-11-2022 to 31-01-2023= 80 days. | Assistant Engineer | ORD/000469/2022-2023 | 678/RSD | 04/11/2022 | 80 | SUMAN CHAKRABORTY, A-7/40, KALYANI, NADIA | 1.19 | 0.21 | 17.65 | 75 | ||
| 4 | NADIA | Nadia Division | Providing Functional House Tap Connection from Teinpur Zone-III Water Supply Scheme (Phase-I) of Retrofitting under Jal Swapna Program in Nadia District under Nadia Division, P.H.E Dte. , SM/08663 | Retrofitting | Material Requisition To Resource Division | RTOR000071/2021-2022 | 804/ND | 18/02/2022 | 0 | Resource Division | 8.78 | 0.00 | 0 | 0 | |||
| 5 | NADIA | Nadia Division | Providing Functional House Tap Connection from Teinpur Zone-III Water Supply Scheme (Phase-I) of Retrofitting under Jal Swapna Program in Nadia District under Nadia Division, P.H.E Dte. , SM/08663 | Retrofitting | Providing functional household tap connection (Part) including supply of 15mm dia PVC pipe of average length of 15 m, Saddle piece (as required size) 15mm dia Bib cock etc. all complete from Teinpur zone - III W/S scheme under Nadia Division, PHE Dte. | Assistant Engineer | ORD/000196/2021-2022 | 5142/ND | 15/09/2021 | 90 | BIDYUT KUMAR | 85.70 | 69.53 | 81.13 | 100 | ||
| Total | 107.01 | 70.41 | 65.79 | ||||||||||||||