| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 9 | 255.63 | 87.73 | 34.32 | ||||||||||||||
| 1 | NADIA | Nadia Division | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). , SM/08134 | Retrofitting | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). | VCH/000610/2021-2022 | 279/PFMS | 08/10/2021 | 0 | TAPU SAHA | 33.12 | 0.00 | 0 | 0 | |||
| 2 | NADIA | Nadia Division | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). , SM/08134 | Retrofitting | Providing functional household tap connection (Part) including supply of 15mm dia PVC pipe of average length of 15 m, 10mm dia Gun-Metal Ferrule, Saddle piece (as required size) 15mm dia Bib cock etc. all complete from Badlangi Padmamala Zone - I W/S scheme (Phase - I) of Retrofitting in Nadia District under Nadia Division P.H.E. Dte." (PART- A) | Assistant Engineer | Junior Engineer Chapra Block | ORD/000006/2021-2022 | 2045/ND | 13/05/2021 | 60 | TAPU SAHA | 42.45 | 0.00 | 0 | 100 | |
| 3 | NADIA | Nadia Division | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). , SM/08134 | Retrofitting | Material Requisition To Resource Division | RTOR000021/2021-2022 | 104/ND | 06/01/2022 | 0 | Resource Division | 0.86 | 0.00 | 0 | 0 | |||
| 4 | NADIA | Nadia Division | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). , SM/08134 | Retrofitting | Material Requisition To Resource Division | RTOR000053/2021-2022 | 436/ND | 31/01/2022 | 0 | Resource Division | 0.63 | 0.00 | 0 | 0 | |||
| 5 | NADIA | Nadia Division | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). , SM/08134 | Retrofitting | Material Requisition To Resource Division | RTOR000109/2021-2022 | 1027/ND | 03/03/2022 | 0 | Resource Division | 6.33 | 0.00 | 0 | 0 | |||
| 6 | NADIA | Nadia Division | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). , SM/08134 | Retrofitting | Material Requisition To Resource Division | RTOR000027/2022-2023 | 4019/ND | 16/09/2022 | 0 | Resource Division | 24.55 | 0.00 | 0 | 0 | |||
| 7 | NADIA | Nadia Division | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). , SM/08134 | Retrofitting | Scheme Information Board at various water supply schemes under Nadia Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer 2 | ORD/000490/2023-2024 | 283/ND | 11/01/2024 | 60 | BIBHAS PAL | 96.01 | 1.94 | 2.02 | 81 | |
| 8 | NADIA | Nadia Division | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). , SM/08134 | Retrofitting | Providing functional household tap connection (Part) including supply of 15mm dia PVC pipe of average length of 15 m, 10mm dia Gun-Metal Ferrule, Saddle piece (as required size) 15mm dia Bib cock etc. all complete from Badlangi Padmamala Zone - I W/S scheme (Phase - I) of Retrofitting in Nadia District under Nadia Division P.H.E. Dte." (PART- C) | Assistant Engineer | ORD/000059/2021-2022 | 2390/ND | 10/06/2021 | 45 | BIPLAB GUHA | 9.23 | 17.76 | 192.42 | 100 | ||
| 9 | NADIA | Nadia Division | Providing Functional House Tap Connection from Badlangi Padmamala Zone-I Water Supply Scheme under Jal Swapno Programme in Nadia District (Phase-I Retrofitting). , SM/08134 | Retrofitting | Providing functional household tap connection (Part) including supply of 15mm dia PVC pipe of average length of 15 m, 10mm dia Gun-Metal Ferrule, Saddle piece (as required size) 15mm dia Bib cock etc. all complete from Badlangi Padmamala Zone - I W/S scheme (Phase - I) of Retrofitting in Nadia District under Nadia Division P.H.E. Dte." (PART- B) | Assistant Engineer | ORD/000007/2021-2022 | 2046/ND | 13/05/2021 | 60 | TAPU SAHA | 42.45 | 68.03 | 160.26 | 100 | ||
| Total | 255.63 | 87.73 | 34.32 | ||||||||||||||