| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 3 | 160.78 | 171.23 | 106.5 | ||||||||||||||
| 1 | NADIA | Nadia Division | Providing FHTC at Surface Water Based Water Supply Scheme (Northern Sector), Part-II, Zone-V within Nakashipara Block (Phase-A). , SM/07497 | Retrofitting | Providing FHTC at Surface Water Based Water Supply Scheme (Northern Sector), Part-II, Zone-V within Nakashipara Block (Phase-A). | VCH/001007/2020-2021 | 25/03/2021 | 0 | UMWELT ENGINEERS PVT LTD | 59.66 | 0.00 | 0 | 0 | ||||
| 2 | NADIA | Nadia Division | Providing FHTC at Surface Water Based Water Supply Scheme (Northern Sector), Part-II, Zone-V within Nakashipara Block (Phase-A). , SM/07497 | Retrofitting | Providing FHTC at Surface Water Based Water Supply Scheme (Northern Sector),Part-II, Zone-V within Nakashipara Block(Phase-A) in Nadia District under Nadia Division P.H.E.Dte.(SL.2) | Assistant Engineer | Junior Engineer 3 | ORD/000465/2020-2021 | 971/ND | 25/02/2021 | 90 | UMWELT ENGINEERS PVT LTD | 97.00 | 171.23 | 176.53 | 0 | |
| 3 | NADIA | Nadia Division | Providing FHTC at Surface Water Based Water Supply Scheme (Northern Sector), Part-II, Zone-V within Nakashipara Block (Phase-A). , SM/07497 | Retrofitting | Material Requisition To Resource Division | RTOR000096/2021-2022 | 818/ND | 18/02/2022 | 0 | Resource Division | 4.12 | 0.00 | 0 | 0 | |||
| Total | 160.78 | 171.23 | 106.5 | ||||||||||||||