| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6 | 233.43 | 14.72 | 6.31 | ||||||||||||||
| 1 | NADIA | Nadia Division | Providing Functional House Tap Connection from Bablari Dewanganj Water Supply Scheme under Jal Swapno Programme , SM/07456 | Retrofitting | Providing Functional House Tap Connection from Bablari Dewanganj Water Supply Scheme under Jal Swapno Programme. | VCH/000991/2020-2021 | 24/03/2021 | 0 | S.S. ENTERPRISE | 44.96 | 0.00 | 0 | 0 | ||||
| 2 | NADIA | Nadia Division | Providing Functional House Tap Connection from Bablari Dewanganj Water Supply Scheme under Jal Swapno Programme , SM/07456 | Retrofitting | Providing Functional House Tap Connection from Bablari Dewanganj Water Supply Scheme under Jal Swapno Programme | VCH/000467/2021-2022 | 264/PFMS | 08/10/2021 | 0 | S.S. ENTERPRISE | 35.02 | 0.00 | 0 | 0 | |||
| 3 | NADIA | Nadia Division | Providing Functional House Tap Connection from Bablari Dewanganj Water Supply Scheme under Jal Swapno Programme , SM/07456 | Retrofitting | PROVIDING FHTC AT BABLARI DEYANGANJ W/S SCHEME UNDER JAL SWAPNO PROGRAM. | VCH/000204/2021-2022 | 89/PPMS | 15/07/2021 | 0 | S.S. ENTERPRISE | 44.96 | 0.00 | 0 | 0 | |||
| 4 | NADIA | Nadia Division | Providing Functional House Tap Connection from Bablari Dewanganj Water Supply Scheme under Jal Swapno Programme , SM/07456 | Retrofitting | Providing functional household tap connection (Part) including supply of 15mm dia PVC pipe of average length of 15 m, 10mm dia Gun-Metal Ferrule, Saddle piece (as required size) 15mm dia Bib cock etc. all complete from Bablari Dewanganj W/S scheme in Nadia District under Nadia Division P.H.E. Dte. | Assistant Engineer | ORD/000239/2020-2021 | 44/ND | 06/01/2021 | 90 | S.S. ENTERPRISE | 97.07 | 14.72 | 15.16 | 100 | ||
| 5 | NADIA | Nadia Division | Providing Functional House Tap Connection from Bablari Dewanganj Water Supply Scheme under Jal Swapno Programme , SM/07456 | Retrofitting | Material Requisition To Resource Division | RTOR000015/2021-2022 | 93/ND | 06/01/2022 | 0 | Resource Division | 7.71 | 0.00 | 0 | 0 | |||
| 6 | NADIA | Nadia Division | Providing Functional House Tap Connection from Bablari Dewanganj Water Supply Scheme under Jal Swapno Programme , SM/07456 | Retrofitting | Material Requisition To Resource Division | RTOR000095/2021-2022 | 792/ND | 18/02/2022 | 0 | Resource Division | 3.71 | 0.00 | 0 | 0 | |||
| Total | 233.42 | 14.72 | 6.31 | ||||||||||||||