| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 8 | 217.2 | 5.65 | 2.6 | ||||||||||||||
| 1 | NADIA | Nadia Division | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) , SM/07419 | Retrofitting | PROVIDING FHTC AT SURFACE BASED W/S SCHEME NORTHERN SECTOR PART-I,ZONE-VI,WITHIN KALIGANJ BLOCK PHASE-A | VCH/000207/2021-2022 | 82/PPMS | 15/07/2021 | 0 | M/S ASOKE GHOSH & BROTHER | 30.57 | 0.00 | 0 | 0 | |||
| 2 | NADIA | Nadia Division | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) , SM/07419 | Retrofitting | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) | VCH/000064/2021-2022 | 12/04/2021 | 0 | M/S ASOKE GHOSH & BROTHER | 30.57 | 0.00 | 0 | 0 | ||||
| 3 | NADIA | Nadia Division | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) , SM/07419 | Retrofitting | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) | VCH/000145/2022-2023 | 08/PFMS | 26/04/2022 | 0 | M/S ASOKE GHOSH & BROTHER | 49.45 | 0.00 | 0 | 0 | |||
| 4 | NADIA | Nadia Division | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) , SM/07419 | Retrofitting | Laying of pipeline at Kaliganj Bazar under Kaliganj G.P under Zone -VI of Surface Water Based Water Supply Scheme, Nadia District Northern Sector (Part-I) under Debagram Sub Division P.H.E Dte.(S.I. No - 04.) | Assistant Engineer | ORD/000610/2021-2022 | 586/DSD | 31/12/2021 | 30 | AVINABA ENGINEERING CONCERN | 0.49 | 0.47 | 95.92 | 0 | ||
| 5 | NADIA | Nadia Division | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) , SM/07419 | Retrofitting | Providing FHTC at Surface Water Based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block ( Phase -A) | Assistant Engineer | Junior Engineer 1 | ORD/000199/2020-2021 | 4088/ND | 31/12/2020 | 90 | M/S ASOKE GHOSH & BROTHER | 96.89 | 5.18 | 5.35 | 100 | |
| 6 | NADIA | Nadia Division | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) , SM/07419 | Retrofitting | Material Requisition To Resource Division | RTOR000173/2023-2024 | 308/ND | 15/01/2024 | 0 | Resource Division | 2.02 | 0.00 | 0 | 0 | |||
| 7 | NADIA | Nadia Division | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) , SM/07419 | Retrofitting | Material Requisition To Resource Division | RTOR000174/2023-2024 | 309/ND | 15/01/2024 | 0 | Resource Division | 1.52 | 0.00 | 0 | 0 | |||
| 8 | NADIA | Nadia Division | Providing FHTC at Surface Water based Water Supply Scheme (Northern Sector), Part-I, Zone-VI within Kaliganj Block (Phase- A) , SM/07419 | Retrofitting | Material Requisition To Resource Division | RTOR000175/2023-2024 | 310/ND | 15/01/2024 | 0 | Resource Division | 5.69 | 0.00 | 0 | 0 | |||
| Total | 217.19 | 5.65 | 2.6 | ||||||||||||||