Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Showing 1 to 9 of 9 entries
Sl No.District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrustedName of JE entrustedSystem Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 87.2400 
Sl No.
District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted
Name of JE entrusted
System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9
87.24
0
0
 
Total
87.26
0.00
0
 
1 PURBA BARDHAMAN Central Mechanical Solarisation of WBSEDCL energised electrical installation at PWSS PART-II at different Blocks under CentralMechanical Division,PHED District Purba Bardhaman , SM/18991 Solarisation of WBSEDCL energised electrical installations at PWSS of different Blocks in the district Purba Bardhaman under Central Mechanical Division, PHE Dte. ORD/001091/2023-2024 4675/CMD 02/11/2023 180 A K INDUSTRIES 85.51 0.00 0 0
2 PURBA BARDHAMAN Central Mechanical Solarisation of WBSEDCL energised electrical installation at PWSS PART-II at different Blocks under CentralMechanical Division,PHED District Purba Bardhaman , SM/18991 WBSEDCL Solar quotation for Lohana PH-1, PWSS. BILL/00147/2024-2025 BP-2024-25-65 06/05/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 0.31 0.00 0 0
3 PURBA BARDHAMAN Central Mechanical Solarisation of WBSEDCL energised electrical installation at PWSS PART-II at different Blocks under CentralMechanical Division,PHED District Purba Bardhaman , SM/18991 WBSEDCL solar quotation for Sajiara PH-1, PWSS. BILL/00148/2024-2025 BP-2024-25-64 06/05/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 0.31 0.00 0 0
4 PURBA BARDHAMAN Central Mechanical Solarisation of WBSEDCL energised electrical installation at PWSS PART-II at different Blocks under CentralMechanical Division,PHED District Purba Bardhaman , SM/18991 Quotation for installation of Solar Plant (Net Billing) at Tendul W/S Scheme PH-1. BILL/00860/2024-2025 BP-2024-25-328 03/10/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 0.22 0.00 0 0
5 PURBA BARDHAMAN Central Mechanical Solarisation of WBSEDCL energised electrical installation at PWSS PART-II at different Blocks under CentralMechanical Division,PHED District Purba Bardhaman , SM/18991 Quotation for installation of solar plant at Natu W/S Scheme for PH-1 BILL/00859/2024-2025 BP-2024-25-329 03/10/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 0.22 0.00 0 0
6 PURBA BARDHAMAN Central Mechanical Solarisation of WBSEDCL energised electrical installation at PWSS PART-II at different Blocks under CentralMechanical Division,PHED District Purba Bardhaman , SM/18991 Quotation for installation of Solar Plant (Net billing) at Murga W/S Scheme PH-2. BILL/00861/2024-2025 BP-2024-25-327 03/10/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 0.22 0.00 0 0
7 PURBA BARDHAMAN Central Mechanical Solarisation of WBSEDCL energised electrical installation at PWSS PART-II at different Blocks under CentralMechanical Division,PHED District Purba Bardhaman , SM/18991 Quotation for new electric solar service connection at Kaity PWSS TW-1 BILL/01089/2024-2025 BP-2024-25-399 22/11/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 0.22 0.00 0 0
8 PURBA BARDHAMAN Central Mechanical Solarisation of WBSEDCL energised electrical installation at PWSS PART-II at different Blocks under CentralMechanical Division,PHED District Purba Bardhaman , SM/18991 Quotation for solar power at Bhatar Z-I TW-1 PWSS BILL/00825/2024-2025 BP-2024-25-330 03/10/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 0.01 0.00 0 0
9 PURBA BARDHAMAN Central Mechanical Solarisation of WBSEDCL energised electrical installation at PWSS PART-II at different Blocks under CentralMechanical Division,PHED District Purba Bardhaman , SM/18991 Quotation for new Solar service connection at Khandaghosh PWSS TW-1 BILL/01090/2024-2025 BP-2024-25-400 22/11/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 0.22 0.00 0 0
Total 87.260.000 
Showing 1 to 9 of 9 entries