Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 633.29 47.8 7.55  
1 PURBA BARDHAMAN Central Mechanical AUGMENTATION OF JHAUDANGA (PART-B) PIPED WATER SUPPLY SCHEME , SM/16293 Augmentation Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination system and internal House wiring for Tube well no.- 1 & 2 at Augmentation of JHAUDANGA( Part-B)[ PURBASTHALI-II] Water Supply Scheme under CMD, PHE Dte., Dist.- Purba-Bardhaman. ORD/001084/2023-2024 4475/CMD 05/10/2023 30 ELECTRICAL & MECHANICAL ENGINEERING CORPORATION 24.19 0.00 0 0
2 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF JHAUDANGA (PART-B) PIPED WATER SUPPLY SCHEME , SM/16293 Augmentation Sinking of 250 X 150mm dia Tube Well 150 mtr. Depth by D.R. Rig method using UPVC pipe (CM) and UPVC Deep Well Screen (RMS) for 1ST TW Site of JHAUDANGA & its adjoining mouzas Piped Water Supply Scheme, Block Purbasthali II, Dist - Purba Bardhaman under Burdwan Division, PHE Dte. Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000720/2023-2024 273/BWD 16/01/2024 30 AUXILIARY TUBE WELL DRILLERS 8.64 5.49 63.54 1
3 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF JHAUDANGA (PART-B) PIPED WATER SUPPLY SCHEME , SM/16293 Augmentation Construction Pump house and construction (As per drawing no-PHE/SE/CC/PH/DWG-01/ 2022-2023) of new (In same place) Pump House No-2 of JHAUDANGA Water Supply Scheme within Kalna Sub-Division under Burdwan Division, PHE Dte. Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000709/2023-2024 4521/BWD 12/10/2023 60 IYASIN DAFADAR 6.76 3.29 48.67 15
4 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF JHAUDANGA (PART-B) PIPED WATER SUPPLY SCHEME , SM/16293 Augmentation Different types of works involve in connection with Augmentation of JHAUDANGA (SM/16293), KASHIPUR (SM/16297), PATULI (SM/09718) & PARULIA (SM/09719) Piped water supply scheme under Purbasthali-II Block, Kalna Sub-Division, PHE Dte. Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000163/2024-2025 2202/BWD 13/06/2024 120 MONDAL PRECISION PVT LTD 570.00 39.02 6.85 2
5 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF JHAUDANGA (PART-B) PIPED WATER SUPPLY SCHEME , SM/16293 Augmentation Digital structurization of pipeline alignment and asset evaluation including holistic design, preparation of design drawings of overall LDS & preparation of estimate for 09 Nos. Piped W/S. Schemes under Purbasthali II Block under Kalna Sub-Division under Burdwan Division, PHE. Dte. Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000338/2024-2025 3018/BWD 05/08/2024 50 HORIZEN 23.70 0.00 0 10
Total 633.29 47.80 7.55