Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 571.3 74.01 12.95  
1 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF SUDPUR PIPED WATER SUPPLY SCHEME , SM/15573 Augmentation Augmentation of SUDPUR Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, Construction of 450 cum capacity RCC OHR with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under KATWA-II Block, District:- Purba-Bardhaman._2ND CALL Assistant Engineer JE RWS ORD/000658/2023-2024 4122/BWD 14/09/2023 840 INDIAN ENGINEERS CO.-OPERATIVE SOCIETY LTD. 442.27 42.09 9.52 63
2 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF SUDPUR PIPED WATER SUPPLY SCHEME , SM/15573 Augmentation Balance work of OHR at Head Work site, construction of HUME Pipe culvert , Road restoration work and boundary wall at 2nd TW site with Gate, land development at Head work site and 2nd TW site under KAITHAN, SUDPUR & PANUHAT Piped Water Supply Scheme under KATWA -I Block, under Katwa Sub-Division within Burdwan Division, PHE Dte. Assistant Engineer JUNIOR ENGINEER KATWA SUB-DIVISION PHE DTE ORD/000486/2024-2025 3141/BWD 20/08/2024 120 VISHAL CONSTRUCTION CO. 126.29 31.92 25.28 50
3 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF SUDPUR PIPED WATER SUPPLY SCHEME , SM/15573 Augmentation Operation &maintenance of Distribution System , Rising main, Sluice Valves, including operation of sluice valves of Sudpur PWSS under Katwa-I Block within Katwa Sub-Division under Burdwan Division, PHE Dte. [Period 01.01.2026 to 28.02.2026 i e 02(Two) Months(Above 30 KM pipeline)(Sl No-14) Assistant Engineer JUNIOR ENGINEER KATWA SUB-DIVISION PHE DTE ORD/001332/2025-2026 2247/KTS 31/12/2025 59 INDIAN ENGINEERS CO.-OPERATIVE SOCIETY LTD. 0.90 0.00 0 0
4 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF SUDPUR PIPED WATER SUPPLY SCHEME , SM/15573 Augmentation Operation & Maintenance of Distribution System , Rising main, Sluice Valves, including operation of sluice valves of SUDPUR PWSS under Katwa-I Block within Katwa Sub-Division under Burdwan Division, PHE Dte. [Period for 01.11.2025 to 31.12.2025 i.e 02(Two) Months].(Sl No-3) ORD/001139/2025-2026 2043-C/KTS 31/10/2025 61 INDIAN ENGINEERS CO.-OPERATIVE SOCIETY LTD. 0.92 0.00 0 0
5 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF SUDPUR PIPED WATER SUPPLY SCHEME , SM/15573 Augmentation Operation &maintenance of Distribution System , Rising main, Sluice Valves, including operation of sluice valves of Sudpur PWSS under Katwa-I Block within Katwa Sub-Division under Burdwan Division, PHE Dte. [Period 01.03.2026 to 30.04.2026 i e 02(Two) Months(Above 30 KM pipeline) (Sl No-6) Assistant Engineer JUNIOR ENGINEER KATWA SUB-DIVISION PHE DTE ORD/001334/2025-2026 163-B/KTS 27/02/2026 61 INDIAN ENGINEERS CO.-OPERATIVE SOCIETY LTD. 0.92 0.00 0 0
Total 571.30 74.02 12.96