| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 5 | 170.62 | 98.6 | 57.79 | ||||||||||||||
| 1 | PURBA BARDHAMAN | Burdwan Division | AUGUMENTATION OF GROUND WATER BASED PIPE WATER SUPPLY SCHEME FOR HATGOBINDAPUR , SM/15175 | Augmentation | Preparation and Submission of DPR for Augmentation of Hatgobindapur PWSS under Burdwan-II Development Block under Burdwan Division, P.H.E Dte.[2nd Call] | Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. | Junior Engineer, Burdwan Sadar Sub-Division | ORD/000350/2023-2024 | 1477/BSD | 12/07/2023 | 15 | MEASURE LAND | 0.78 | 0.77 | 98.72 | 100 | |
| 2 | PURBA BARDHAMAN | Burdwan Division | AUGUMENTATION OF GROUND WATER BASED PIPE WATER SUPPLY SCHEME FOR HATGOBINDAPUR , SM/15175 | Augmentation | Construction of 300 cu.m. capacity 20 mtr staging height RCC Over Head Reservoir including Pipe connection & soil investigation under HATGOBINDAPUR Piped W/S. Scheme within Burdwan - II Block under Burdwan Division, P.H.E Dte. | Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE.,ASSISTANT ENGINEER R.W.S. BURDWAN SUB-DIVISION PHE DTE | Junior Engineer, Burdwan Sadar Sub-Division | ORD/000014/2023-2024 | 1729/BWD | 13/04/2023 | 537 | GUPTA ENTERPRISE | 89.36 | 70.50 | 78.89 | 100 | |
| 3 | PURBA BARDHAMAN | Burdwan Division | AUGUMENTATION OF GROUND WATER BASED PIPE WATER SUPPLY SCHEME FOR HATGOBINDAPUR , SM/15175 | Augmentation | Laying of interconnection between 1st & 2nd tube well to OHR for Hatgobindapur PWSS within Burdhaman-II Block under Burdwan Division, PHE Dte. | Junior Engineer, Burdwan Sadar Sub-Division | ORD/001065/2024-2025 | 103/BSD | 16/01/2025 | 46 | I.S. ENTERPRISE | 3.60 | 0.00 | 0 | 100 | ||
| 4 | PURBA BARDHAMAN | Burdwan Division | AUGUMENTATION OF GROUND WATER BASED PIPE WATER SUPPLY SCHEME FOR HATGOBINDAPUR , SM/15175 | Augmentation | Different works related (Sinking of Tube well-4th, Rising Main, construction of Pump House cum switch room and Boundary wall for HATGOBINDAPUR Piped Water Supply Scheme under BURDWAN -II Block, District:- Purba-Bardhaman. | Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. | Junior Engineer, Burdwan Sadar Sub-Division | ORD/000280/2024-2025 | 2712/BWD | 11/07/2024 | 264 | DEY NIRMAN | 41.51 | 27.33 | 65.84 | 100 | |
| 5 | PURBA BARDHAMAN | Burdwan Division | AUGUMENTATION OF GROUND WATER BASED PIPE WATER SUPPLY SCHEME FOR HATGOBINDAPUR , SM/15175 | Augmentation | Providing LDS in place of AC pipe line for HATGOBINDAPUR PWSS under Bardhaman-II Block within Burdwan Div. PHE Dte. | Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. | Junior Engineer, Burdwan Sadar Sub-Division | ORD/001278/2024-2025 | 874/BWD | 06/03/2025 | 177 | DEY NIRMAN | 35.37 | 0.00 | 0 | 100 | |
| Total | 170.63 | 98.59 | 57.78 | ||||||||||||||