Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 1,442.92 199.38 13.82  
1 PURBA BARDHAMAN Raina-II Burdwan Division Katnabil Piped Water Supply Scheme , SM/13338 New Material Requisition To Resource Division RTOR000375/2023-2024 2197/BWD 12/05/2023 0 Resource Division 4.23 0.00 0 0
2 PURBA BARDHAMAN Raina-II Burdwan Division Katnabil Piped Water Supply Scheme , SM/13338 New Material Requisition To Resource Division RTOR000512/2023-2024 4036/BWD 08/09/2023 0 Resource Division 4.83 0.00 0 0
3 PURBA BARDHAMAN Raina-II Burdwan Division Katnabil Piped Water Supply Scheme , SM/13338 New Material Requisition To Resource Division RTOR000673/2023-2024 5050/BWD 23/11/2023 0 Resource Division 20.46 0.00 0 0
4 PURBA BARDHAMAN Raina-II Central Mechanical Katnabil Piped Water Supply Scheme , SM/13338 New New service connection charges for Katnabil PWSS TW-1 BILL/01700/2023-2024 BP-2023-24-231 20/11/2023 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 7.27 0.00 0 0
5 PURBA BARDHAMAN Raina-II Central Mechanical Katnabil Piped Water Supply Scheme , SM/13338 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Satinandi,Sanko & others water supply scheme under Galsi-1 Block ; Serpur, Uchalan & others water supply scheme under Raina-2 Block and maro, loapur & others water supply scheme under Galsi-2 block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000397/2024-2025 2751/CMD 24/09/2024 90 ORIENTAL ENGINEERING CO. 88.42 0.00 0 0
6 PURBA BARDHAMAN Raina-II Central Mechanical Katnabil Piped Water Supply Scheme , SM/13338 New New Service connection for Katnabil W/S Scheme PH No.-II BILL/01800/2023-2024 BP-2023-24-300 30/12/2023 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 10.15 0.00 0 0
7 PURBA BARDHAMAN Raina-II Burdwan Division Katnabil Piped Water Supply Scheme , SM/13338 New Different works related (sinking of Tube-wells, LDSs, Rising Mains, FHTCs, Construction of different capacity RCC OHRs each with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drains and internal pathways at different TW site) to UCHALAN, CHAK CHANDAN, SERPUR & KATNABIL Piped Water Supply Scheme under Raina II Block, District:- Purba Bardhaman [NEW SCHEME] Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE ORD/000367/2023-2024 3076/BWD 18/07/2023 806 SK ALIM 1,307.56 199.38 15.25 75
Total 1,442.92 199.38 13.82