Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 407.33 131.33 32.24  
1 PURBA BARDHAMAN Purbasthali - I Burdwan Division HARIPUR PIPED WATER SUPPLY SCHEME , SM/13315 New Material Requisition To Resource Division RTOR000152/2023-2024 2155/BWD 10/05/2023 Resource Division 10.75 0.00 0 0
2 PURBA BARDHAMAN Purbasthali - I Central Mechanical HARIPUR PIPED WATER SUPPLY SCHEME , SM/13315 New New service connection charges for Haripur PWSS TW-1 BILL/00820/2023-2024 BP-2023-24-97 02/08/2023 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 3.02 0.00 0 0
3 PURBA BARDHAMAN Purbasthali - I Burdwan Division HARIPUR PIPED WATER SUPPLY SCHEME , SM/13315 New Material Requisition To Resource Division RTOR000521/2023-2024 4284/BWD 29/09/2023 Resource Division 0.55 0.00 0 0
4 PURBA BARDHAMAN Purbasthali - I Central Mechanical HARIPUR PIPED WATER SUPPLY SCHEME , SM/13315 New Supply & Installation of Submersible Pumping Machinery , Voltage Stabilizer, Chlorination System and Internal House wiring for Tube well no.- 1 & 2 at HARIPUR Water Supply Scheme [Block - PURBASTHALI-1] under CMD, PHE Dte., Dist.- Purba-Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000164/2023-2024 2931/CMD 12/07/2023 30 ASHIM UDYOG 20.77 9.37 45.11 30
5 PURBA BARDHAMAN Purbasthali - I Burdwan Division HARIPUR PIPED WATER SUPPLY SCHEME , SM/13315 New Material Requisition To Resource Division RTOR000599/2023-2024 4905/BWD 10/11/2023 Resource Division 4.86 0.00 0 0
6 PURBA BARDHAMAN Purbasthali - I Burdwan Division HARIPUR PIPED WATER SUPPLY SCHEME , SM/13315 New HARIPUR Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under Purbasthali I Block, District:- Purba-Bardhaman [NEW SCHEME]. Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000774/2022-2023 1340/BWD 22/03/2023 90 INVENT ENGINEERS CO. OPERATIVE SOCIETY LTD. 94.46 57.64 61.02 55
7 PURBA BARDHAMAN Purbasthali - I Central Mechanical HARIPUR PIPED WATER SUPPLY SCHEME , SM/13315 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Haripur & others water supply scheme under purbasthali 1 Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000072/2024-2025 2397/CMD 02/08/2024 90 CHATTERJEE ENTERPRISE 48.60 0.00 0 0
8 PURBA BARDHAMAN Purbasthali - I Burdwan Division HARIPUR PIPED WATER SUPPLY SCHEME , SM/13315 New Different Types of work involved in connection with Augmentation of NAOPARA (SM/09407) & HARIPUR (SM/13315) water supply scheme Piped water supply scheme within Kalna Sub-Division under Burdwan Division, PHE Dte. Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000164/2024-2025 2203/BWD 13/06/2024 120 MONDAL & CO. 223.65 64.32 28.76 50
9 PURBA BARDHAMAN Purbasthali - I Central Mechanical HARIPUR PIPED WATER SUPPLY SCHEME , SM/13315 New Withdrawing of pump motor set due to low discharge and installation of new pump motor set at Haripur PH 1 (Purbasthali-1 Block) water supply scheme under CMD P.H.E. Dte. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/001893/2023-2024 364/CMSD 28/02/2024 15 ASHIM UDYOG 0.67 0.00 0 0
Total 407.34 131.33 32.24