Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
12 3,597.58 334.87 9.31  
1 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Preparation of DPR for augmentation of Anukhal W/S Scheme within Kalna Sub-Division under Burdwan Division, PHE Dte. (Sl No-D) Assistant Engineer ORD/000570/2021-2022 206/KSD 23/02/2022 21 INDRANIL DUTTA & ASSOCIATES 2.86 2.82 98.6 1
2 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Supply of materials for different water supply scheme under Burdwan Division, PHE Dte. VCH/001578/2021-2022 1207/DW 10/03/2022 EXECUTIVE ENGINEER, RESOURCES DIVISION, P.H.E. DTE. 3,005.00 0.00 0 0
3 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Material Requisition To Resource Division RTOR000210/2021-2022 1533/BWD 15/03/2022 Resource Division 0.37 0.00 0 0
4 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Material Requisition To Resource Division RTOR000133/2021-2022 1204/BWD 04/03/2022 Resource Division 22.68 0.00 0 0
5 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Material Requisition To Resource Division RTOR000055/2021-2022 531/BWD 27/01/2022 Resource Division 14.56 0.00 0 0
6 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Material Requisition To Resource Division RTOR000148/2021-2022 1242/BWD 07/03/2022 Resource Division 4.93 0.00 0 0
7 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Material Requisition To Resource Division RTOR000160/2021-2022 1320/BWD 08/03/2022 Resource Division 32.89 0.00 0 0
8 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Material Requisition To Resource Division RTOR000041/2022-2023 4627/BWD 17/10/2022 Resource Division 12.32 0.00 0 0
9 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Work Order for Supervision and extend support to NABL recognised Water Quality Testing Block level Laboratory under The Assistant Engineer, Kalna Sub-Division, Public Health Engineering Directorate, Government of West Bengal by assigining team of competent resource personnel who will be engeged for complete supervision for retaining NABL recognition and compilation of preparatory up-to-date documentation,Calibration for on-site survelliance by NABL (as per NABL 139) for a period of one month from the date of commencement. (Name of SDL : Anukhal Sub District Water Testing Laboratory under Kalna Sub Division.) Assistant Engineer JUNIOR ENGINEER R.W.S. BURDWAN SUB-DIVISION PHE DTE ORD/000672/2023-2024 1335/KSD 28/08/2023 30 BHARATI CHEMICAL & SCIENTIFIC WORKS 0.91 0.00 0 0
10 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Augmentation of ANUKHAL Piped Water Supply Scheme with LDS, FHTC, Rising main, Construction of 250 cum capacity OHR with 20.0 mtr. Staging height inclusive of soil investigation with construction of boundary wall at Headworks site under Kalna-II Block, District:- Purba-Burdwan. Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000096/2022-2023 2741/BWD 08/06/2022 365 SINGHA ROY AND CO. 374.09 318.48 85.13 70
11 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Sinking of tube well, Laying dist. system, Providing FHTC, construction of Pump House & Boundary and Laying rising main of ANUKHAL Piped Water Supply Scheme within Kalna Sub-Divn. under Burdwan Division, PHE. Dte. Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000857/2023-2024 5206/BWD 29/11/2023 120 SINGHA ROY AND CO. 119.49 9.66 8.08 15
12 PURBA BARDHAMAN Burdwan Division Augmentation of ANUKHAL PWSS for providing Functional Household Tap Connection (FHTC) KALNA-II block under KALNA Sub Division of Burdwan Division in Purba Bardhaman District , SM/09403 Augmentation Additional work to implement augmentation of ANUKHAL Water Supply Scheme within Kalna Sub-Division under Burdwan Division, PHE Dte. Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000821/2023-2024 4998/BWD 21/11/2023 30 UDYOG CONSTRUCTION 7.48 3.91 52.27 100
Total 3,597.57 334.88 9.31