Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 299.7 102.41 34.17  
1 PURBA BARDHAMAN Galsi-I Burdwan Division MARO PIPED WATER SUPPLY SCHEME , SM/15579 New Material Requisition To Resource Division RTOR000027/2023-2024 1962/BWD 25/04/2023 0 Resource Division 3.65 0.00 0 0
2 PURBA BARDHAMAN Galsi-I Burdwan Division MARO PIPED WATER SUPPLY SCHEME , SM/15579 New Material Requisition To Resource Division RTOR000340/2023-2024 2197/BWD 12/05/2023 0 Resource Division 7.00 0.00 0 0
3 PURBA BARDHAMAN Galsi-I Burdwan Division MARO PIPED WATER SUPPLY SCHEME , SM/15579 New Material Requisition To Resource Division RTOR000605/2023-2024 4910/BWD 10/11/2023 0 Resource Division 12.78 0.00 0 0
4 PURBA BARDHAMAN Galsi-I Burdwan Division MARO PIPED WATER SUPPLY SCHEME , SM/15579 New MARO Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under Galsi-I Block, District:- Purba-Bardhaman [NEW SCHEME] Assistant Engineer, Durgapur Sub Division, P.H.E. Dte Junior Engineer1, Durgapur Sub-Division, PHE Dte. ORD/000175/2023-2024 2569/BWD 01/06/2023 120 INVENT ENGINEERS CO. OPERATIVE SOCIETY LTD. 113.32 90.81 80.14 90
5 PURBA BARDHAMAN Galsi-I Central Mechanical MARO PIPED WATER SUPPLY SCHEME , SM/15579 New Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at MARO Water Supply Scheme [ Block- GALSI-1] under CMD, PHE Dte., Dist.- Purba-Bardhaman. Driller In-Charge JUNIOR ENGINEER ORD/000903/2023-2024 4167/CMD 29/08/2023 30 CHOUDHURY ENTERPRISE 28.54 11.60 40.64 48
6 PURBA BARDHAMAN Galsi-I Central Mechanical MARO PIPED WATER SUPPLY SCHEME , SM/15579 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Satinandi,Sanko & others water supply scheme under Galsi-1 Block ; Serpur, Uchalan & others water supply scheme under Raina-2 Block and maro, loapur & others water supply scheme under Galsi-2 block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000397/2024-2025 2751/CMD 24/09/2024 90 ORIENTAL ENGINEERING CO. 88.42 0.00 0 0
7 PURBA BARDHAMAN Galsi-I Central Mechanical MARO PIPED WATER SUPPLY SCHEME , SM/15579 New New service connection for MARO PWSS, PG-1. BILL/02485/2023-2024 BP-2023-24-537 15/02/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 3.06 0.00 0 0
8 PURBA BARDHAMAN Galsi-I Burdwan Division MARO PIPED WATER SUPPLY SCHEME , SM/15579 New Different works related (sinking of Tube-wells at Maro Dakshin Para, LDSs, Interconnections, FHTCs, Construction of MARO Piped Water Supply Scheme for obstruction of Railway under Galsi-I Block, of Durgapur Sub Division, under Burdwan Division, PHE. Dte. Assistant Engineer, Durgapur Sub Division, P.H.E. Dte Junior Engineer1, Durgapur Sub-Division, PHE Dte. ORD/000334/2024-2025 2895/BWD 23/07/2024 371 PREMANANDA ROY BISWAS 42.93 0.00 0 90
Total 299.69 102.42 34.18