Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 1,710.67 150.45 8.79  
1 PURBA BARDHAMAN Ausgram-I Burdwan Division JAYKRISHNAPUR PIPED WATER SUPPLY SCHEME , SM/14073 New Material Requisition To Resource Division RTOR000024/2023-2024 1962/BWD 25/04/2023 0 Resource Division 39.22 0.00 0 0
2 PURBA BARDHAMAN Ausgram-I Burdwan Division JAYKRISHNAPUR PIPED WATER SUPPLY SCHEME , SM/14073 New Material Requisition To Resource Division RTOR000292/2023-2024 2197/BWD 12/05/2023 0 Resource Division 6.23 0.00 0 0
3 PURBA BARDHAMAN Ausgram-I Central Mechanical JAYKRISHNAPUR PIPED WATER SUPPLY SCHEME , SM/14073 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Joykrishnapur & others water supply scheme under Purbasthali-2,jamalpur,kalna 1 Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000101/2024-2025 2398/CMD 02/08/2024 90 MS S G ENTERPRISE 53.43 0.00 0 0
4 PURBA BARDHAMAN Ausgram-I Central Mechanical JAYKRISHNAPUR PIPED WATER SUPPLY SCHEME , SM/14073 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Pichkuri, karatia & others water supply scheme under Ausgram-1 Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman Driller In-Charge JUNIOR ENGINEER ORD/000398/2024-2025 2764/CMD 26/09/2024 90 JAL PRAVAHIKA PVT LTD 52.55 0.00 0 0
5 PURBA BARDHAMAN Ausgram-I Burdwan Division JAYKRISHNAPUR PIPED WATER SUPPLY SCHEME , SM/14073 New Material Requisition To Resource Division RTOR000776/2023-2024 200/BWD 10/01/2024 0 Resource Division 7.26 0.00 0 0
6 PURBA BARDHAMAN Ausgram-I Burdwan Division JAYKRISHNAPUR PIPED WATER SUPPLY SCHEME , SM/14073 New Different works related (sinking of Tube-wells, LDSs, Rising Mains, FHTCs, Construction of different capacity RCC OHRs each with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drains and internal pathways at different TW site) to ALIGRAM, JAYKRISHNAPUR, JADABGANJ & KALYANPUR Piped Water Supply Scheme under AUSGRAM-I Block, District:- Purba-Bardhaman [NEW SCHEME] AE(HQs) JUNIOR ENGINEER R.W.S. BURDWAN SUB-DIVISION PHE DTE ORD/000727/2023-2024 4581/BWD 16/10/2023 965 SAFECO ENTERPRISES 1,551.98 150.45 9.69 60
Total 1,710.67 150.45 8.79