Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 21,703.57 1.33 0.01  
1 BIRBHUM Illambazar Birbhum Division MAHESWARPUR PIPED WATER SUPPLY SCHEME , SM/15254 New Different works related to water supply scheme at MAHESWARPUR Piped Water Supply Scheme within ILLAMBAZAR Block including supply of all labour & materials under Bolpur Sub-Division within Birbhum Division, PHE Dte. AE JE1 ORD/000037/2023-2024 1133/BHM 10/04/2023 270 GUPTA CONSTRUCTION 339.98 0.00 0 0
2 BIRBHUM Illambazar Birbhum Division MAHESWARPUR PIPED WATER SUPPLY SCHEME , SM/15254 New Material Requisition To Resource Division RTOR000118/2023-2024 1584/BHM 26/04/2023 Resource Division 20.97 0.00 0 0
3 BIRBHUM Illambazar Birbhum Division MAHESWARPUR PIPED WATER SUPPLY SCHEME , SM/15254 New Continuation Work Order for "Preparation & Submission of Detail Project Report (DPR) for MAHESHWARPUR Piped Water Supply Scheme under Illambazar Development Block within Bolpur Sub-Division under Birbhum Division, PHE Dte.". AE JE2,Bolpur Sub-Division ORD/001138/2021-2022 108/BSD 21/03/2022 90 M/S R DUTTA & CO. 2.86 1.33 46.5 100
4 BIRBHUM Illambazar Central Drilling MAHESWARPUR PIPED WATER SUPPLY SCHEME , SM/15254 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 300 JHARGRAM SPV PRIVATE LIMITED 21,339.76 0.00 0 11
Total 21,703.57 1.33 0.01