Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 23,509.55 3.69 0.02  
1 BIRBHUM Labpur Birbhum Division FARIDPUR PIPED WATER SUPPLY SCHEME , SM/14971 New Material Requisition To Resource Division RTOR000152/2023-2024 1590/BHM 26/04/2023 0 Resource Division 65.61 0.00 0 0
2 BIRBHUM Labpur Birbhum Division FARIDPUR PIPED WATER SUPPLY SCHEME , SM/14971 New Continuation work order for "Preparation & Submission of Detail Project Report (DPR) for FARIDPUR Piped Water Supply Scheme under Labpur Development Block within Bolpur Sub-Division under Birbhum Division, PHE Dte." AE JE3 ORD/000654/2022-2023 146/BSD 12/04/2022 180 APEX ENGINEERING 4.22 3.69 87.44 100
3 BIRBHUM Labpur Birbhum Division FARIDPUR PIPED WATER SUPPLY SCHEME , SM/14971 New Material Requisition To Resource Division RTOR000009/2024-2025 2397/BHM 27/08/2024 0 Resource Division 8.90 0.00 0 0
4 BIRBHUM Labpur Central Drilling FARIDPUR PIPED WATER SUPPLY SCHEME , SM/14971 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 304 JHARGRAM SPV PRIVATE LIMITED 21,339.76 0.00 0 11
5 BIRBHUM Labpur Birbhum Division FARIDPUR PIPED WATER SUPPLY SCHEME , SM/14971 New Construction of Different capacity O.H.R.,with Soil investigation, 5.90 m X 4.10 mPump room/ Chlorine room with sanitary arrangements, and laying of Rising main,Distribution system, with FHTC .and Construction of boundary wall including approach road and land development at Head work site and 2 nd under different (6 nos).PIPED WATER SUPPLY SCHEME within LABPUR Block including supply of all labour & materials under Bolpur Sub-Division within Birbhum Division, PHE Dte. AE,Assistant Engineer JE,JE1,JE3 ORD/000084/2024-2025 1948/BHM 04/07/2024 730 UMWELT ENGINEER PVT. LTD. 2,014.73 0.00 0 0
6 BIRBHUM Labpur Bolpur Mechanical FARIDPUR PIPED WATER SUPPLY SCHEME , SM/14971 New Construction of Tube Well (300 MM x 200 MM x Depth 450 Mtr) for Faridpur PWSS (TW No I and II), Block- Labpur, in Birbhum District under Bolpur Mechanical Division, P.H.E Dte. Assistant Engineer,Assistant Engineer (HQ) Junior Engineer ORD/001120/2024-2025 327/BOL.MD 19/02/2025 120 OSMAN SEKH 76.33 0.00 0 0
Total 23,509.55 3.69 0.02