| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 3 | 334.16 | 5.4 | 1.62 | ||||||||||||||
| 1 | BIRBHUM | Khoyrasol | Birbhum Division | Haripur Piped Water Supply Scheme , SM/14853 | New | Preparation & Submission of DPR for Pump House cum Chlorine Room, Boundary Wall, Soil Investigation Report, Construction Over Head Reservoir (OHR), Construction of Pipe carrying structure, Service Road at Head Work Site & Land Development, FHTC Connection of Haripur & its adjoining mouzas Piped Water Supply Scheme under Khayrasole Development Block. | AE | JE | ORD/000859/2022-2023 | 93/BSSD | 27/05/2022 | 45 | RADIANT | 2.22 | 2.22 | 100 | 100 |
| 2 | BIRBHUM | Khoyrasol | Birbhum Division | Haripur Piped Water Supply Scheme , SM/14853 | New | Preparation & Submission of DPR for laying distribution of Haripur & its adjoining mouzas Piped Water Supply Scheme under Khayrasole Development Block. | AE | JE | ORD/000858/2022-2023 | 88/BSSD | 20/05/2022 | 45 | RADIANT | 3.18 | 3.18 | 100 | 100 |
| 3 | BIRBHUM | Khoyrasol | Birbhum Division | Haripur Piped Water Supply Scheme , SM/14853 | New | Material Requisition To Resource Division | RTOR000241/2023-2024 | 427/BHM | 01/02/2024 | 0 | Resource Division | 328.76 | 0.00 | 0 | 0 | ||
| Total | 334.15 | 5.40 | 1.62 | ||||||||||||||