Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
12 23,297.84 253.89 1.09  
1 BIRBHUM Bolpur Sriniketan Bolpur Mechanical Albandha Piped Water Supply Scheme. , SM/14533 New Providing Electro-mechanical accessories and others for Albandha & Adjoining moujas water supply scheme at Bolpur Sriniketan Block under Bolpur Mechanical Division PHE Dte. Assistant Engineer Junior Engineer ORD/000478/2023-2024 2238/BOL.MD. 13/09/2023 90 DEY ENTERPRISE 73.35 35.00 47.72 50
2 BIRBHUM Bolpur Sriniketan Birbhum Division Albandha Piped Water Supply Scheme. , SM/14533 New Material Requisition To Resource Division RTOR000104/2023-2024 1547/BHM 26/04/2023 0 Resource Division 219.35 0.00 0 0
3 BIRBHUM Bolpur Sriniketan Bolpur Mechanical Albandha Piped Water Supply Scheme. , SM/14533 New Supply and delivery of 80 mm UPVC standard type column pipe (Cream colour) for albandha water supply scheme(T/W-II) under BOL MD, PHE Dte.. Assistant Engineer (HQ) Junior Engineer ORD/000815/2024-2025 4195/BOL.MD 22/10/2024 20 M. S. ENTERPRISE 2.60 0.00 0 100
4 BIRBHUM Bolpur Sriniketan Bolpur Mechanical Albandha Piped Water Supply Scheme. , SM/14533 New Supply and delivery of column pipe for albandha water supply scheme(T/W-I) under BOL MD, PHE Dte.. Assistant Engineer (HQ) Junior Engineer ORD/000550/2024-2025 3805/BOL.MD 12/09/2024 20 SATYAJIT GHOSH 2.52 2.52 100 100
5 BIRBHUM Bolpur Sriniketan Bolpur Mechanical Albandha Piped Water Supply Scheme. , SM/14533 New Supply and delivery of Submersible pump for albandha Water Supply under Bolpur Mechanical Divn. PHE Dte. Assistant Engineer (HQ) Junior Engineer ORD/000552/2024-2025 3806/BOL.MD 12/09/2024 20 M/S. YOUTH ENGINEERS' ENTERPRISE 2.48 1.12 45.16 100
6 BIRBHUM Bolpur Sriniketan Bolpur Mechanical Albandha Piped Water Supply Scheme. , SM/14533 New Supply & delivery of submersible cable accessories at albandha Piped water supply scheme under Bolpur Mechanical Division, PHE Dte. Assistant Engineer (HQ) Junior Engineer ORD/000572/2024-2025 3843/BOL.MD 18/09/2024 20 UNITED TRADERS 2.15 2.15 100 100
7 BIRBHUM Bolpur Sriniketan Bolpur Mechanical Albandha Piped Water Supply Scheme. , SM/14533 New WBSEDCL QUOTATION FOR ALBANDHA WS SCHEME BILL/01591/2023-2024 BP-23-24-221 15/01/2024 0 WBSEDCL 5.28 0.00 0 0
8 BIRBHUM Bolpur Sriniketan Central Drilling Albandha Piped Water Supply Scheme. , SM/14533 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 304 JHARGRAM SPV PRIVATE LIMITED 21,339.76 17.25 0.08 11
9 BIRBHUM Bolpur Sriniketan Birbhum Division Albandha Piped Water Supply Scheme. , SM/14533 New Different works related to water supply scheme at ALBANDHA, BERGRAM & BIDYADHARPUR Piped Water Supply Scheme within BOLPUR-SRINIKETAN Block including supply of all labour & materials under BIRBHUM Division, PHE Dte. (2nd Call) AE JE4 ORD/000387/2023-2024 4146/BHM 19/10/2023 805 AMAL DUTTA ROY 1,648.21 193.70 11.75 12
10 BIRBHUM Bolpur Sriniketan Birbhum Division Albandha Piped Water Supply Scheme. , SM/14533 New Hiring of 01(One) no. vehicle for the Office of the Assistant Engineer, Bolpur Sub-Division, PHE Dte. under Birbhum Division, PHE Dte. For the period of 01.01.2025 to 30.06.2025. Assistant Engineer JE3 ORD/000543/2024-2025 1237/BSD 31/12/2024 181 RAJIYA BIBI 0.85 0.00 0 0
11 BIRBHUM Bolpur Sriniketan Central Drilling Albandha Piped Water Supply Scheme. , SM/14533 New Hiring of Diesel driven motor cab (BS-III & Above) (Non AC) having contract carriage permit along with driver for the office of the DIC/ CMSD-I P.H.E. Dte. Under CMSD-I(D), CDD, P.H.E. Dte. Driller In Charge Junior Engineer ORD/000054/2024-2025 378/CMSD-I 24/12/2024 182 SUJATA BHOWMICK 0.86 2.15 250 0
12 BIRBHUM Bolpur Sriniketan Birbhum Division Albandha Piped Water Supply Scheme. , SM/14533 New Continuation work order for "Hiring of 01(One) no. vehicle for the Office of the Assistant Engineer, Bolpur Sub-Division, PHE Dte. under Birbhum Division, PHE Dte. For the period of 01.01.2025 to 30.06.2025" for another 03(Three) months i.e. 01.07.2025 to 30.09.2025. Assistant Engineer JE3 ORD/000095/2025-2026 640/BSD 20/06/2025 92 RAJIYA BIBI 0.43 0.00 0 0
Total 23,297.85 253.89 1.09