Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 1,055.42 30.07 2.85  
1 BIRBHUM Sainthia Birbhum Division Kurumsaha Piped Water Supply Scheme. , SM/13628 New Material Requisition To Resource Division RTOR000051/2022-2023 1366/BHM 24/04/2023 Resource Division 19.69 0.00 0 0
2 BIRBHUM Sainthia Central Drilling Kurumsaha Piped Water Supply Scheme. , SM/13628 New PROVIDING DRLLING CREW AND OTHER ALLIED WORKS FOR CONSTRUCTION OF TUBE WELL (250MM X 150MM X 150 MTRS DEPTH) BY UTILISING DEPARTMENTAL MACHINERIES FOR Kurumsaha W/S SCHEME (TW-II), SAINTHIA BLOCK, UNDER BIRBHUM DISTRICT, CDD, PHE DTE. Driller In Charge Junior Engineer ORD/000405/2022-2023 1428/CDD 29/11/2022 30 C.M. ENTERPRISE 10.49 9.15 87.23 0
3 BIRBHUM Sainthia Central Drilling Kurumsaha Piped Water Supply Scheme. , SM/13628 New PROVIDING DRILLING CREWS FOR CONSTRUCTION OF TUBE WELL BY DEPARTMENTAL RIG MACHINE IN KURUMSAHA PWSS (TW-I), BLOCK-SAINTHIA, BIRBHUM DISTRICT UNDER CDD, PHE DTE. ORD/000417/2022-2023 398/CMSD-I 05/08/2022 15 C.M. ENTERPRISE 3.77 2.50 66.31 0
4 BIRBHUM Sainthia Central Drilling Kurumsaha Piped Water Supply Scheme. , SM/13628 New PROVIDING TUBE WELL MATERIALS, CONFORMING TO IS: 12818:2010 WITH OTHER WORKS AT SITE FOR CONSTRUCTION OF TUBE WELL IN KURUMSAHA PWSS (TW-I), SAINTHIA BLOCK, BIRBHUM DISTRICT UNDER CDD, PHE DTE. ORD/000415/2022-2023 382/CMSD-I 05/08/2022 15 C.M. ENTERPRISE 4.18 3.79 90.67 0
5 BIRBHUM Sainthia Central Drilling Kurumsaha Piped Water Supply Scheme. , SM/13628 New SUPPLY & DELIVERY OF CONSUMBLES WITH OTHER WORKS AT SITE FOR CONSTTRUCTION OF TUBE WELL IN KURUMSAHA PWSS (TW-I), BLOCK-SAINTHIA, BIRBHUM DISTRICT UNDER CDD, PHE DTE. ORD/000416/2022-2023 390/CMSD-I 05/08/2022 15 C.M. ENTERPRISE 2.66 2.64 99.25 0
6 BIRBHUM Sainthia Bolpur Mechanical Kurumsaha Piped Water Supply Scheme. , SM/13628 New WBSEDCL QUOTATION FOR KURUMSAHA P.H.NO.I BILL/00707/2023-2024 BP-2023-2024-63 02/08/2023 WBSEDCL 3.85 0.00 0 0
7 BIRBHUM Sainthia Bolpur Mechanical Kurumsaha Piped Water Supply Scheme. , SM/13628 New wbsedcl quotation for kurumsaha p.h.no.ii ws scheme BILL/00716/2023-2024 BP-23-24-70 09/08/2023 WBSEDCL 3.91 0.00 0 0
8 BIRBHUM Sainthia Bolpur Mechanical Kurumsaha Piped Water Supply Scheme. , SM/13628 New Providing Electro-mechanical accessories and others for Kurumsaha & Adjoining moujas water supply scheme at Sainthia Block under Bolpur Mechanical Division PHE Dte. Driller in Charge Junior Engineer ORD/000418/2023-2024 2090/Bol.MD 22/08/2023 60 MITRA ENTERPRISE 28.04 11.99 42.76 80
9 BIRBHUM Sainthia Birbhum Division Kurumsaha Piped Water Supply Scheme. , SM/13628 New Different works related to water supply scheme at DERPUR, KURUMSAHA & MATIARA and its adjoining mouzas water supply scheme within SAINTHIA Block including supply of all labour & materials under Birbhum Division, PHE Dte. AE JE ORD/000056/2023-2024 1245/BHM 17/04/2023 270 BRAHMA CONSTRUCTION COMPANY 978.83 0.00 0 65
Total 1,055.41 30.07 2.85