Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 2,649.15 0 0  
1 BIRBHUM Dubrajpur Birbhum Division Paratpur Piped Water Supply Scheme. , SM/13474 New Material Requisition To Resource Division RTOR000073/2022-2023 1401/BHM 24/04/2023 Resource Division 70.19 0.00 0 0
2 BIRBHUM Dubrajpur Birbhum Division Paratpur Piped Water Supply Scheme. , SM/13474 New Material Requisition To Resource Division RTOR000187/2023-2024 3279/BHM 27/07/2023 Resource Division 2.05 0.00 0 0
3 BIRBHUM Dubrajpur Bolpur Mechanical Paratpur Piped Water Supply Scheme. , SM/13474 New Providing Electro-mechanical accessories and others for Paratpur & Adjoining moujas water supply scheme at Dubrajpur Block under Bolpur Mechanical Division PHE Dte. Assistant Engineer-III Junior Engineer ORD/000937/2023-2024 3394/Bol.MD 17/10/2023 90 EASTERN INDIA SALES & SERVICE 79.72 0.00 0 0
4 BIRBHUM Dubrajpur Birbhum Division Paratpur Piped Water Supply Scheme. , SM/13474 New Different works related to water supply scheme at CHINPAI, LOBA & PARATPUR and its adjoining mouzas water supply scheme within DUBRAJPUR Block including supply of all labour & materials under BIRBHUM Division, PHE Dte AE JE1 ORD/000265/2023-2024 3476/BHM 08/08/2023 270 B RAI CONSTRUCTION COMPANY 2,497.19 0.00 0 45
Total 2,649.15 0.00 0