Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 347.66 112.03 32.22  
1 BIRBHUM Birbhum Division Retrofitting works for providing functional household tap connection (FHTC) under Sadasibpur (Bisor) PWSS within Murarai-II Block District Birbhum under Birbhum Division, PHE Dte. , SM/09366 Retrofitting Supply & delivery of Sluice Valve for augmentation of Sadashibpur (Bisor) W/S Scheme under Birbhum Division, PHE Dte including loading, carriage and uploading at Birbhum Divisional Store at PHE Complex, Dist.-Birbhum under Birbhum Division, PHE Dte. (Sl. No.-03) AE(HQ) ORD/000805/2021-2022 715/BHM 31/03/2022 15 MAKALI ENGINEERING CORPORATION 4.99 0.00 0 100
2 BIRBHUM Birbhum Division Retrofitting works for providing functional household tap connection (FHTC) under Sadasibpur (Bisor) PWSS within Murarai-II Block District Birbhum under Birbhum Division, PHE Dte. , SM/09366 Retrofitting Balance works of Laying Distribution system at Sadasibpur, Kendishta, Chhatina and Amudda habitations under Sadashibpur W/S Scheme under Nalhati Sub-Division, within Birbhum Division P.H.E Dte.. (SL.No.5) AE JE1 ORD/000826/2021-2022 498/BHM 02/03/2022 45 SUPER SKILL 47.00 0.00 0 100
3 BIRBHUM Birbhum Division Retrofitting works for providing functional household tap connection (FHTC) under Sadasibpur (Bisor) PWSS within Murarai-II Block District Birbhum under Birbhum Division, PHE Dte. , SM/09366 Retrofitting Restoration of concrete road including dismantling of Water Supply Scheme For Sadashibpur and it's adjoining Mouzas under Nalhati Sub-Division, within Birbhum Division P.H.E Dte. AE JE1 ORD/000105/2022-2023 356/AE/NSD 20/07/2022 60 SUPER SKILL 4.83 0.00 0 100
4 BIRBHUM Birbhum Division Retrofitting works for providing functional household tap connection (FHTC) under Sadasibpur (Bisor) PWSS within Murarai-II Block District Birbhum under Birbhum Division, PHE Dte. , SM/09366 Retrofitting Supply & delivery of Sluice Valve for Sadashibpur (Bishor) W/S Scheme under Birbhum Division, PHE Dte including loading, carriage and uploading at Birbhum Divisional Store at PHE Complex, Dist.-Birbhum under Birbhum Division, PHE Dte (Sl. No.-03) AE(HQ) ORD/000132/2022-2023 1243/BHM 03/06/2022 15 MAKALI ENGINEERING CORPORATION 4.99 0.00 0 100
5 BIRBHUM Birbhum Division Retrofitting works for providing functional household tap connection (FHTC) under Sadasibpur (Bisor) PWSS within Murarai-II Block District Birbhum under Birbhum Division, PHE Dte. , SM/09366 Retrofitting Balance work for Pump House at Head Work site of Sadashibpur PWSS under Nalhati Sub-Division within Birbhum Division, PHED. AE JE1 ORD/000686/2021-2022 168/AE/NSD 22/03/2022 15 SUBHRANIL DAS 0.83 0.00 0 100
6 BIRBHUM Birbhum Division Retrofitting works for providing functional household tap connection (FHTC) under Sadasibpur (Bisor) PWSS within Murarai-II Block District Birbhum under Birbhum Division, PHE Dte. , SM/09366 Retrofitting Material Requisition To Resource Division RTOR000037/2021-2022 213/BHM 02/02/2022 Resource Division 15.63 0.00 0 0
7 BIRBHUM Birbhum Division Retrofitting works for providing functional household tap connection (FHTC) under Sadasibpur (Bisor) PWSS within Murarai-II Block District Birbhum under Birbhum Division, PHE Dte. , SM/09366 Retrofitting Balance work of distribution pipeline including extention of pipeline along with FHTC and restoration of roads alongwith Construction of 500 M³ capacity 20.00 Mtr. staging height RCC Over Head Reservoir at Sadasibhpur W/S Scheme within Nalhati Sub-Division under Birbhum Division, P.H.E. Dte.(Sl. No.3) AE JE1 ORD/000385/2022-2023 2857/BHM 22/12/2022 180 SUPER SKILL 175.35 52.24 29.79 90
8 BIRBHUM Birbhum Division Retrofitting works for providing functional household tap connection (FHTC) under Sadasibpur (Bisor) PWSS within Murarai-II Block District Birbhum under Birbhum Division, PHE Dte. , SM/09366 Retrofitting Providing Functional Household Tap Connection (FHTC) from existing distribution system within the command area of Sadashibpur (Bisor) Water Supply Scheme within Nalhati Sub-Division Birbhum Division, PHE Dte. (Sl. No.1) AE JE1 ORD/000018/2022-2023 822/BHM 13/04/2022 60 QUAZI SIRAJUL ISLAM. 94.04 59.79 63.58 100
Total 347.66 112.03 32.22