Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 857.07 319.39 37.27  
1 MURSHIDABAD Murshidabad Division Augmentation of KHARGRAM Piped Water Supply Scheme Block -Khargram District - Murshidabad. , SM/18737 Augmentation Material Requisition To Resource Division RTOR000066/2022-2023 1278/MURD/15 10/05/2023 0 Resource Division 26.34 0.00 0 0
2 MURSHIDABAD Murshidabad Division Augmentation of KHARGRAM Piped Water Supply Scheme Block -Khargram District - Murshidabad. , SM/18737 Augmentation Material Requisition To Resource Division RTOR000343/2023-2024 79/MURD/10 09/01/2024 0 Resource Division 28.50 0.00 0 0
3 MURSHIDABAD Murshidabad Division Augmentation of KHARGRAM Piped Water Supply Scheme Block -Khargram District - Murshidabad. , SM/18737 Augmentation Material Requisition To Resource Division RTOR000361/2023-2024 MURD/439/14 08/02/2024 0 Resource Division 25.58 0.00 0 0
4 MURSHIDABAD Berhampore Mechanical Augmentation of KHARGRAM Piped Water Supply Scheme Block -Khargram District - Murshidabad. , SM/18737 Augmentation Providing, installation and commissioning of submersible pumping machinery along with allied Electro-Mechanical works for Augmentation in connection to Accommodate FHTC at Pump House No.-I of KHARGRAM ground water based water supply scheme under Block- KHARGRAM Dist. Murshidabad under MEDB, PHE Dte. ASSISTANT ENGINEER-II Junior engineer-II ORD/000056/2023-2024 3239/MEDB 22/08/2023 679 DAS ENTERPRISE (CHOA) 12.27 0.00 0 40
5 MURSHIDABAD Murshidabad Division Augmentation of KHARGRAM Piped Water Supply Scheme Block -Khargram District - Murshidabad. , SM/18737 Augmentation Construction of 700 Cum OHR, Boundary Wall, Rising Main Connection, Laying Distribution System PART-A,FHTC at Village- KHARGRAM (Vill. code- 315195) & Village- KANDURI (Vill. code- 315166) for Augmentation of KHARGRAM PWSS in Khargram Block , under Murshidabad Division ,PHE. Dte Part-A ASSISTANT ENGINEER JUNIOR ENGINEER 1 ORD/000266/2023-2024 2572/MURD 18/08/2023 699 M/S. S. DAS AND ENTERPRISE 393.75 113.08 28.72 10
6 MURSHIDABAD Murshidabad Division Augmentation of KHARGRAM Piped Water Supply Scheme Block -Khargram District - Murshidabad. , SM/18737 Augmentation Laying Distribution System PART-B and FHTC at Vill-KHARGRAM (Village Code-315195) & Vill-DURGAPUR (Village Code-315167) for Augmentation of KHARGRAM PWSS in Khargram Block, under Murshidabad Division ,PHE. Dte Part-B ASSISTANT ENGINEER JUNIOR ENGINEER 1 ORD/000268/2023-2024 2573/MURD 18/08/2023 561 M/S. S. DAS AND ENTERPRISE 370.63 206.31 55.66 5
Total 857.07 319.39 37.26