Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 392.02 74.97 19.12  
1 MURSHIDABAD Khargram Murshidabad Division MAHAMMADPUR AND IT'S ADJOINING MOUJAS PWSS , SM/13936 New Material Requisition To Resource Division RTOR000023/2023-2024 1067/MURD/6 18/04/2023 Resource Division 24.66 0.00 0 0
2 MURSHIDABAD Khargram Berhampore Mechanical MAHAMMADPUR AND IT'S ADJOINING MOUJAS PWSS , SM/13936 New Name of Work: Providing, installation and commissioning of submersible pumping machinery along with allied Electro-Mechanical works for Newly Sunk Tube Well in connection to Accommodate FHTC at Pump House No.-I & II under MAHAMMADPUR ground water based water supply scheme under Block_ Khargram, Dist. - Murshidabad under MEDB, PHE Dte. ASSISTANT ENGINEER-II Junior engineer-II ORD/000158/2023-2024 2016/MEDB 19/06/2023 90 A.G. ENTERPRISE 20.38 0.00 0 0
3 MURSHIDABAD Khargram Murshidabad Division MAHAMMADPUR AND IT'S ADJOINING MOUJAS PWSS , SM/13936 New Material Requisition To Resource Division RTOR000336/2023-2024 79/MURD/03 09/01/2024 Resource Division 8.45 0.00 0 0
4 MURSHIDABAD Khargram Murshidabad Division MAHAMMADPUR AND IT'S ADJOINING MOUJAS PWSS , SM/13936 New Material Requisition To Resource Division RTOR000350/2023-2024 112/MURD/07 11/01/2024 Resource Division 8.45 0.00 0 0
5 MURSHIDABAD Khargram Berhampore Mechanical MAHAMMADPUR AND IT'S ADJOINING MOUJAS PWSS , SM/13936 New new service connection at MAHAMMADPUR PH2 ID304222150 BILL/01146/2023-2024 228/WBSEDCL-JJM 09/01/2024 WBSEDCL 4.75 0.00 0 0
6 MURSHIDABAD Khargram Berhampore Mechanical MAHAMMADPUR AND IT'S ADJOINING MOUJAS PWSS , SM/13936 New new service connection at MAHAMMADPUR PH2 ID304222150 BILL/01146/2023-2024 228/WBSEDCL-JJM 09/01/2024 WBSEDCL 4.75 0.00 0 0
7 MURSHIDABAD Khargram Berhampore Mechanical MAHAMMADPUR AND IT'S ADJOINING MOUJAS PWSS , SM/13936 New NEW SERVICE CONNECTION AT MAHHAMMADPUR PH1 ID304222178 BILL/01147/2023-2024 229/WBSEDCL-JJM 09/01/2024 WBSEDCL 2.70 0.00 0 0
8 MURSHIDABAD Khargram Berhampore Mechanical MAHAMMADPUR AND IT'S ADJOINING MOUJAS PWSS , SM/13936 New NEW SERVICE CONNECTION AT MAHHAMMADPUR PH1 ID304222178 BILL/01147/2023-2024 229/WBSEDCL-JJM 09/01/2024 WBSEDCL 2.70 0.00 0 0
9 MURSHIDABAD Khargram Murshidabad Division MAHAMMADPUR AND IT'S ADJOINING MOUJAS PWSS , SM/13936 New Formal work order for the work of MAHAMMADPUR & adjoining moujas PWSS to accommodate FHTC, Construction Tube Well, OHR, Pump House Cum Chlorine Room, Laying Distribution System, Rising Main, boundary wall and service road, under Jal Jevan Mission of Murshidabad District under Murshidabad Division, PHE.Dte. ASSISTANT ENGINEER JUNIOR ENGINEER 2 ORD/000710/2022-2023 143/MURD 17/01/2023 365 SUJIT KUMAR SAHA 315.18 74.97 23.79 70
Total 392.01 74.97 19.13