Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 315.29 97.62 30.96  
1 MURSHIDABAD Burwan Murshidabad Division JUGASWARA AND ADJOINING MOUJAS PWSS , SM/13724 New Material Requisition To Resource Division RTOR000008/2023-2024 1210/MURD/37 02/05/2023 Resource Division 1.42 0.00 0 0
2 MURSHIDABAD Burwan Murshidabad Division JUGASWARA AND ADJOINING MOUJAS PWSS , SM/13724 New Sinking of 02(Two) Nos 250mm x 150 mm dia tube well 100.00 mtr. deep by direct rotary rig method using UPVC Pipe and UPVC Deep Well Screen (RDS) filter at JUGASWARA PWSS at Head Work Site & 2nd Tube Well Site in Burwan Block under Kandi Sub-Division, Murshidabad Division, P.H.Engineering Dte. ASSISTANT ENGINEER JUNIOR ENGINEER_BURWAN BLOCK ORD/000770/2022-2023 485/MURD 20/02/2023 45 NADIA TUBEWELLS 16.81 15.07 89.65 100
3 MURSHIDABAD Burwan Murshidabad Division JUGASWARA AND ADJOINING MOUJAS PWSS , SM/13724 New Material Requisition To Resource Division RTOR000346/2023-2024 112/MURD/03 11/01/2024 Resource Division 4.88 0.00 0 0
4 MURSHIDABAD Burwan Berhampore Mechanical JUGASWARA AND ADJOINING MOUJAS PWSS , SM/13724 New Providing, installation and commissioning of submersible pumping machinery along with allied Electro-Mechanical works for Augmentation in connection to Accommodate FHTC at Pump House No.-I & II of Jugaswara ground water based water supply scheme under Block- Burwan, Dist. Murshidabad under MEDB, PHE Dte. ASSISTANT ENGINEER-I Junior engineer-II ORD/000098/2023-2024 1889/MEDB 16/06/2023 90 ASSOCIATED ELECTRICAL CO. 21.23 7.28 34.29 20
5 MURSHIDABAD Burwan Berhampore Mechanical JUGASWARA AND ADJOINING MOUJAS PWSS , SM/13724 New NEW SERVICE CONNECTION AT PWSS PH1 JUGASWARA ID 304240312 BILL/01418/2023-2024 311/WBSEDCL-JJM 05/02/2024 WBSEDCL 4.88 0.00 0 0
6 MURSHIDABAD Burwan Berhampore Mechanical JUGASWARA AND ADJOINING MOUJAS PWSS , SM/13724 New NEW SERVICE CONNECTION AT PWSS PH1 JUGASWARA ID 304240312 BILL/01418/2023-2024 311/WBSEDCL-JJM 05/02/2024 WBSEDCL 4.88 0.00 0 0
7 MURSHIDABAD Burwan Berhampore Mechanical JUGASWARA AND ADJOINING MOUJAS PWSS , SM/13724 New NEW SERVICE CONNECTION AT PWSS PH 2 JUGASWARA ID 304240283 BILL/01419/2023-2024 312/WBSEDCL-JJM 05/02/2024 WBSEDCL 9.89 0.00 0 0
8 MURSHIDABAD Burwan Murshidabad Division JUGASWARA AND ADJOINING MOUJAS PWSS , SM/13724 New Formal Work Order ForConstruction of 100 Cum OHR, Pump House at Head Work Site & 2nd Tube well site , Laying Distribution System, Rising Main, FHTC, Boundary wall of JUGASWARA PWSS in Burwan Block , Kandi Sub-Division under Murshidabad Division ,PHE.Dte. ( Scheme ID -PH222362271S000) [(i)Amount for LDS , R.Main & FHTC: Rs.1,38,33,206.00 & (ii) Amount for OHR, Boundwary Wall & Pump House : Rs. 1,13,02,060.00] ASSISTANT ENGINEER JUNIOR ENGINEER_BURWAN BLOCK ORD/000757/2022-2023 416/MURD 15/02/2023 365 SHYAMAL KUMAR SAHA 251.30 75.27 29.95 70
Total 315.30 97.63 30.96