Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 813.13 257.14 31.62  
1 MALDAH Kaliachak-I Malda Mechanical Khaschandpur mouza piped water supply scheme of Kaliachak-I block under Malda arsenic area water supply Division, PHED. , SM/17177 New W.B.S.E.D.C.LTD Quotation charge at P/H No. I of Khaschandpur PWSS, Kaliachak C.C.C in the district of Malda Under Malda Mechanical Division PHE Dte. Assistant Engineer - II ORD/001011/2023-2024 3004427011 18/09/2023 90 W.B.S.E.D.C.LTD 11.07 11.07 100 100
2 MALDAH Kaliachak-I Malda Ars Area W/S Division Khaschandpur mouza piped water supply scheme of Kaliachak-I block under Malda arsenic area water supply Division, PHED. , SM/17177 New Material Requisition To Resource Division RTOR000011/2023-2024 636/MAAD 05/04/2023 0 Resource Division 67.64 0.00 0 0
3 MALDAH Kaliachak-I Malda Ars Area W/S Division Khaschandpur mouza piped water supply scheme of Kaliachak-I block under Malda arsenic area water supply Division, PHED. , SM/17177 New Construction of 500 Cum capacity 20 Mtr. staging height RCC Over Head Reservoir as per Departmental Design & Drawing including pipe connection, Soil Investigation and Providing Functional House Hold Tap Connection (FHTC) for Khaschandpur Piped Water Supply scheme at Kaliachak-I Block under Malda Arsenic Area W/S Division, P.H.E. Dte, Malda. .(2nd Call) Assistant Engineer-I,Assistant Engineer-II Junior Engineer-II ORD/000053/2023-2024 956/MAAD 29/05/2023 583 BEE GEE CONSTRUCTION 218.56 109.16 49.95 85
4 MALDAH Kaliachak-I Malda Ars Area W/S Division Khaschandpur mouza piped water supply scheme of Kaliachak-I block under Malda arsenic area water supply Division, PHED. , SM/17177 New Sinking of Two nos 250mm. Dia. x 150mm. big dia. Tube Well of 150 Mtr. deep by Direct Rotary Rig method using UPVC (CM) Pipes & UPVC Medium Well Screen (RMS) Pipes with Ribs for Khaschandpur Piped Water supply scheme (Head Work Site & 2nd Tube well site) at Kaliachak-I Block under Malda Arsenic Area Water Supply Division , P.H.E. Dte., Malda Assistant Engineer-II Junior Engineer-II ORD/000318/2022-2023 597/MAAD 30/03/2023 45 M/S S.S. ENTERPRISE 14.72 9.04 61.41 100
5 MALDAH Kaliachak-I Malda Ars Area W/S Division Khaschandpur mouza piped water supply scheme of Kaliachak-I block under Malda arsenic area water supply Division, PHED. , SM/17177 New Construction of Arsenic-cum-Iron Removal Plant (AIRP) for Khaschandpur Piped Water supply scheme at Kaliachak-I Block under Malda Arsenic Area W/S Division, P.H.E.Dte. in the District of Malda.(2nd Call) Assistant Engineer-I,Assistant Engineer-II Junior Engineer-II ORD/000020/2023-2024 867/MAAD 04/05/2023 698 NEOGI ENTERPRISE 168.73 60.34 35.76 85
6 MALDAH Kaliachak-I Malda Ars Area W/S Division Khaschandpur mouza piped water supply scheme of Kaliachak-I block under Malda arsenic area water supply Division, PHED. , SM/17177 New Laying of Distribution System at Dalal More, Gaddha More, Hindupara for Khaschandpur Piped Water supply scheme at Kaliachak-I Block under Malda Arsenic Area W/S Division, P.H.E.Dte. In the District of Malda. Assistant Engineer-I,Assistant Engineer-II Junior Engineer-II ORD/000009/2023-2024 693/MAAD 13/04/2023 444 MILLENNIUM ENTERPRISE 87.26 0.00 0 90
7 MALDAH Kaliachak-I Malda Mechanical Khaschandpur mouza piped water supply scheme of Kaliachak-I block under Malda arsenic area water supply Division, PHED. , SM/17177 New Supply, delivery, installation and trial operation of Electro-Mechanical components and allied works at Ground Water Based Tube Well No-I & II and Arsenic Iron Removal Plant at Khaschandpur Piped Water Supply Scheme in the district of Malda Under Malda Mechanical Division, PHE Dte. Assistant Engineer - II Junior Engineer-03 ORD/001731/2023-2024 3389/MLMD 31/10/2023 789 GHOSH BROTHERS... 70.55 0.00 0 0
8 MALDAH Kaliachak-I Malda Ars Area W/S Division Khaschandpur mouza piped water supply scheme of Kaliachak-I block under Malda arsenic area water supply Division, PHED. , SM/17177 New Construction of Boundary Wall at Head Work Site & 2nd Tube Well Site, Laying of rising main from 2nd Tube Well Site to HWS including supply of all specials & valves and Providing Functional House Hold Tap Connection (FHTC) for Khaschandpur Piped Water Supply scheme at Kaliachak-I Block under Malda Arsenic Area W/S Division, P.H.E. Dte, Malda. Assistant Engineer-I Junior Engineer-II ORD/000238/2024-2025 1692/MAAD 19/11/2024 90 BEE GEE CONSTRUCTION 70.37 0.00 0 0
9 MALDAH Kaliachak-I Malda Ars Area W/S Division Khaschandpur mouza piped water supply scheme of Kaliachak-I block under Malda arsenic area water supply Division, PHED. , SM/17177 New Laying of Distribution System at Dawan Tola, Charka Tola, Maksaha Tola, Patuatola Chandpur, Haginagar Chandpur for Khaschandpur Piped Water supply scheme at Kaliachak-I Block under Malda Arsenic Area W/S Division, P.H.E.Dte. In the District of Malda. Assistant Engineer-I,Assistant Engineer-II Junior Engineer-II ORD/000459/2022-2023 575/MAAD 28/03/2023 614 M/S TRILOCHAN CONSTRUCTION CO. 104.23 67.53 64.79 100
Total 813.13 257.14 31.62