Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 113.73 83.42 73.35  
1 MALDAH Malda Division INSTALLATION OF 18 nos. STAND ALONE COMMUNITY PURIFICATION PLANT (CWPP) AT SCHOOLS OF OLD MALDA DEV BLOCK ,MALDA UNDER MALDA DIVISION,PHE DTE. , SM/10241 School Material Requisition To Resource Division RTOR000013/2021-2022 530/MD 03/03/2022 0 Resource Division 24.82 0.00 0 0
2 MALDAH Malda Division INSTALLATION OF 18 nos. STAND ALONE COMMUNITY PURIFICATION PLANT (CWPP) AT SCHOOLS OF OLD MALDA DEV BLOCK ,MALDA UNDER MALDA DIVISION,PHE DTE. , SM/10241 School Acceptance cum formal work order for Installation of Stand-Alone Community Purification Plant (CWPP) at different Schools of Old Malda Dev. Block, Malda under Malda Division, PHE Dte. Mr. Arnab Giri, Assistant Engineer Bikash Balo, Junior Engineer,Ramen Karmakar, Junior Engineer ORD/000001/2022-2023 830/MD 06/04/2022 90 NEOGI ENTERPRISE 88.91 83.42 93.83 100
Total 113.72 83.42 73.35