Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 13,042.03 153.55 1.18  
1 UTTAR DINAJPUR Goalpokhar-II Raiganj Division DAKSHIN NEAMATPUR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/16491 New Material Requisition To Resource Division RTOR000145/2022-2023 838/RD/PHE 23/03/2023 0 Resource Division 41.51 0.00 0 0
2 UTTAR DINAJPUR Goalpokhar-II Malda Mechanical DAKSHIN NEAMATPUR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/16491 New Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I & II and making compound lighting arrangement at T/W no. I of Dakshin Neamatpur Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/015935) Assistant Engineer - I Junior Engineer-02 ORD/000485/2023-2024 2491/MLMD 04/08/2023 787 NABAUDYAG ELECTRICAL ENGINEERING CO-OPERATIV SOCIETY LTD. 26.45 19.13 72.33 72
3 UTTAR DINAJPUR Goalpokhar-II Malda Mechanical DAKSHIN NEAMATPUR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/16491 New Quotation for new service connection at DAKSHIN NEAMATPUR PH-II (Kanki ccc) in the district of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (SM/16491) BILL/01089/2024-2025 BP-2024-25-264 05/06/2024 0 W.B.S.E.D.C.LTD 5.41 0.00 0 0
4 UTTAR DINAJPUR Goalpokhar-II Malda Mechanical DAKSHIN NEAMATPUR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/16491 New Quotation for new service connection at DAKSHIN NEAMATPUR PH-I (Kanki ccc) in the district of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (SM/16491) BILL/01088/2024-2025 BP-2024-25-263 05/06/2024 0 W.B.S.E.D.C.LTD 5.41 0.00 0 0
5 UTTAR DINAJPUR Goalpokhar-II Raiganj Division DAKSHIN NEAMATPUR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/16491 New Additional pipeline and other ancillary works at Dakshin Neamatpur piped water Supply Scheme Under Islampur Sub -Division under Raiganj Division,P.H.E Dte. Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000407/2025-2026 2366/RD/PHE 26/08/2025 45 MILAN GHOSH 32.18 0.00 0 0
6 UTTAR DINAJPUR Goalpokhar-II Raiganj Division DAKSHIN NEAMATPUR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/16491 New Sinking of Tube Well, laying of rising main & distribution system, providing FHTC ,Construction of Over Head Reservoir over Pile / Raft Foundation including subsoil investigation, construction of Pump House, Chlorine room, Boundary Wall & Approach Road and allied works for 25 nos. Piped water supply Schemes within GOALPOKHAR-II Dev. Block of Uttar Dinajpur District under Raiganj Division ,PHE Dte. Assistant Engineer ISD JUNIOR ENGINEER,Junior Engineer, ISD ORD/000374/2023-2024 2590/RD/PHE 11/09/2023 810 M/S GHOSH AND CO. 12,931.07 134.42 1.04 35
Total 13,042.03 153.54 1.18