Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 410.26 127.04 30.97  
1 UTTAR DINAJPUR Itahar Raiganj Division Gorahar Piped Water Supply Scheme. , SM/14640 New Preparation and submission of DPR for drinking Water Supply Scheme to facilitate uncovered mouzas under Uttar Dinajpur District, Block- Itahar. Assistant Engineer RSD ORD/000576/2022-2023 1770/RD/PHE 19/09/2022 15 RADIANT 47.87 3.60 7.52 100
2 UTTAR DINAJPUR Itahar Raiganj Division Gorahar Piped Water Supply Scheme. , SM/14640 New Material Requisition To Resource Division RTOR000060/2023-2024 2230/RD/PHE 01/08/2023 0 Resource Division 24.45 0.00 0 0
3 UTTAR DINAJPUR Itahar Raiganj Division Gorahar Piped Water Supply Scheme. , SM/14640 New Construction of Boundary Wall With Gate at Head Work Site & 2nd Tube-Well Site under GORAHAR PWSS at Itahar Block under Raiganj Division, PHE Dte. Assistant Engineer HQ,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000493/2023-2024 613/RD/PHE 05/03/2024 45 M/S NATARAJ CONSTRUCTION DEBUABCD.1234@REDIFFMAIL.COM 22.58 0.00 0 0
4 UTTAR DINAJPUR Itahar Malda Mechanical Gorahar Piped Water Supply Scheme. , SM/14640 New Quotation for new service connection at GORAHAR PH-I (Itahar ccc) in the district of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. BILL/03740/2023-2024 BP-2023-24-691 15/03/2024 0 W.B.S.E.D.C.LTD 5.55 0.00 0 0
5 UTTAR DINAJPUR Itahar Malda Mechanical Gorahar Piped Water Supply Scheme. , SM/14640 New Quotation for new service connection at GORAHAR PH-II (Birnagar ccc) in the district of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. BILL/03741/2023-2024 BP-2023-24-692 15/03/2024 0 W.B.S.E.D.C.LTD 5.89 0.00 0 0
6 UTTAR DINAJPUR Itahar Malda Mechanical Gorahar Piped Water Supply Scheme. , SM/14640 New Additional Quotation for new service connection at GORAHAR PH-I (ITAHAR ccc) in the district of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (SM/14640) BILL/02078/2024-2025 BP-2024-25-484 09/09/2024 0 W.B.S.E.D.C.LTD 3.44 0.00 0 0
7 UTTAR DINAJPUR Itahar Malda Mechanical Gorahar Piped Water Supply Scheme. , SM/14640 New Additional Quotation for TW No- II of Gorahar Water supply scheme, Birnagar CCC in the dist of Uttar Dinajpur Under Malda Mechanical Division PHE Dte. BILL/01597/2024-2025 BP-2024-25-398 29/07/2024 0 W.B.S.E.D.C.LTD 2.39 0.00 0 0
8 UTTAR DINAJPUR Itahar Raiganj Division Gorahar Piped Water Supply Scheme. , SM/14640 New Implementation of GORAHAR and it's adjoining mouzas Pipe Water Supply Scheme at ITAHAR Block of Uttar Dinajpur District under Raiganj Division, PHE Dte. Assistant Engineer RSD Junior Engineer, RSD ORD/000315/2022-2023 564/RD/PHE 23/02/2023 1042 SANYAL ENTERPRISE 243.13 104.94 43.16 38
9 UTTAR DINAJPUR Itahar Malda Mechanical Gorahar Piped Water Supply Scheme. , SM/14640 New Supply, installation, commissioning and trial operation of electro-mechanical components of T/W no- I,II & Making compound yard lighting arrangement at T/W no- I of GORAHAR Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/016130) Assistant Engineer - I Junior Engineer-02 ORD/001697/2023-2024 3422/MLMD 01/11/2023 720 MAA BHABOTARINE ENTERPRISE 25.16 18.50 73.53 78
10 UTTAR DINAJPUR Itahar Raiganj Division Gorahar Piped Water Supply Scheme. , SM/14640 New Balance pipe line for providing functional household tap connection (FHTC), approach road with land development of headwork site & 2nd tubewell site and road restoration of Gorahar PWSS at Itahar Block under Raiganj Division, PHE Dte., Uttar Dinajpur. Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000478/2024-2025 11/RD/PHE 02/01/2025 45 AJIT PRAMANIK 29.80 0.00 0 0
Total 410.27 127.03 30.96