Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 6,688.51 0 0  
1 UTTAR DINAJPUR Goalpokhar-I Malda Mechanical GOALIN Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12784 New Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I & II and making compound lighting arrangement at T/W no. I of Goalin Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/014474) Assistant Engineer - I ORD/000541/2023-2024 2501/MLMD 04/08/2023 120 A.G ENTERPRISE. 29.41 0.00 0 0
2 UTTAR DINAJPUR Goalpokhar-I Raiganj Division GOALIN Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12784 New Material Requisition To Resource Division RTOR000013/2023-2024 1125/RD/PHE 24/04/2023 0 Resource Division 43.90 0.00 0 0
3 UTTAR DINAJPUR Goalpokhar-I Raiganj Division GOALIN Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12784 New Additional pipeline, Pathway, Land development and other ancillary works at GOALIN piped water Supply Scheme Under Islampur Sub-Division under Raiganj Division, P.H.E Dte. Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000375/2025-2026 2289/RD/PHE 12/08/2025 120 DEEP CONSTRUCTION 78.53 0.00 0 0
4 UTTAR DINAJPUR Goalpokhar-I Raiganj Division GOALIN Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12784 New Providing FHTC in connection with Goalin Pipe Water Supply Scheme at Goalpukhur-I Block of Uttar Dinajpur District under Raiganj Division.(New PWSS) (2nd Call) Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000276/2025-2026 2181/RD/PHE 29/07/2025 90 MAA TARA CONSTRUCTION (SEVOKPALLY) RGJMAATARA@GMAIL.COM 6.17 0.00 0 0
5 UTTAR DINAJPUR Goalpokhar-I Raiganj Division GOALIN Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12784 New Sinking of Tube Well, laying of rising main & distribution system, providing FHTC ,Construction of Over Head Reservoir over Pile / Raft Foundation including subsoil investigation, construction of Pump House, Chlorine room, Boundary Wall & Approach Road and allied works for 16 nos. Piped water supply Schemes within GOALPOKHAR-I Dev. Block of Uttar Dinajpur District under Raiganj Division, PHE Dte. Assistant Engineer ISD Junior Engineer, ISD ORD/000373/2023-2024 2568/RD/PHE 01/09/2023 805 ROY ENGINEERS. (PATNA) 6,530.50 0.00 0 38
Total 6,688.51 0.00 0