Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 6,687.83 157.81 2.36  
1 UTTAR DINAJPUR Goalpokhar-I Raiganj Division CHHOTA PATNA Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12780 New Material Requisition To Resource Division RTOR000020/2023-2024 1126/RD/PHE 24/04/2023 0 Resource Division 36.82 0.00 0 0
2 UTTAR DINAJPUR Goalpokhar-I Malda Mechanical CHHOTA PATNA Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12780 New Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I & II and making compound lighting arrangement at T/W no. I of Chhota Patna Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/014398) Assistant Engineer - I Junior Engineer-02 ORD/000467/2023-2024 2482/MLMD 04/08/2023 840 MAA BHABOTARINE ENTERPRISE. 27.46 0.00 0 73
3 UTTAR DINAJPUR Goalpokhar-I Malda Mechanical CHHOTA PATNA Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12780 New Quotation for new service connection at Choto Patna PH-I (Goalpokher ccc) BILL/03521/2023-2024 BP-2023-24-541 15/02/2024 0 W.B.S.E.D.C.LTD 12.08 0.00 0 0
4 UTTAR DINAJPUR Goalpokhar-I Malda Mechanical CHHOTA PATNA Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12780 New Quotation for new service connection at Choto Patna PH-II (Goalpokher ccc) BILL/03520/2023-2024 BP-2023-24-540 15/02/2024 0 W.B.S.E.D.C.LTD 10.71 0.00 0 0
5 UTTAR DINAJPUR Goalpokhar-I Raiganj Division CHHOTA PATNA Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12780 New Sinking of Tube Well, laying of rising main & distribution system, providing FHTC ,Construction of Over Head Reservoir over Pile / Raft Foundation including subsoil investigation, construction of Pump House, Chlorine room, Boundary Wall & Approach Road and allied works for 16 nos. Piped water supply Schemes within GOALPOKHAR-I Dev. Block of Uttar Dinajpur District under Raiganj Division, PHE Dte. Assistant Engineer ISD Junior Engineer, ISD ORD/000373/2023-2024 2568/RD/PHE 01/09/2023 805 ROY ENGINEERS. (PATNA) 6,530.50 157.81 2.42 38
6 UTTAR DINAJPUR Goalpokhar-I Raiganj Division CHHOTA PATNA Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12780 New Laying of additional pipeline for improving FHTC with ancillary works at different mouzas at CHOTA PATNA PWSS Of Goalpokhar-1 Block under Islampur Sub-Division P.H.E. Dte. Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000017/2025-2026 1201/RD/PHE 25/04/2025 45 HAQUE CONSTRUCTION 39.32 0.00 0 0
7 UTTAR DINAJPUR Goalpokhar-I Raiganj Division CHHOTA PATNA Piped Water Supply Scheme at Goalpokhar-I Block under Uttar Dinajpur District. , SM/12780 New Designing, Supplying, Febrication, Erection on suitable RCC foundation, commissioning with 3(three) months Trial Run (including cost of routine testing of water sample and flow/hr for performance evaluation) of pressure type Iron Removal Plant as per design norms of CPHEEO(latest) with necessary accessories for Chotopatna Water Supply Scheme at Goalpukhur-I Block under Raiganj Division, P.H.E. Dte. Dist:- Uttar Dinajpur, Capacity- 70 M3/hr. Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000325/2025-2026 1996/RD/PHE 07/07/2025 180 UNIVERSAL ENGINEERS CO-OPERATIVE SOCIETY LTD. 30.94 0.00 0 0
Total 6,687.82 157.81 2.36