| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 9 | 665.86 | 370.21 | 55.6 | ||||||||||||||
| 1 | UTTAR DINAJPUR | Raiganj Division | AUGMENTATION GOALPOKHER PIPED WATER SUPPLY SCHEME , SM/11726 | Augmentation | Material Requisition To Resource Division | RTOR000032/2022-2023 | 1944/RD/PHE | 04/11/2022 | 0 | Resource Division | 33.97 | 0.00 | 0 | 0 | |||
| 2 | UTTAR DINAJPUR | Malda Mechanical | AUGMENTATION GOALPOKHER PIPED WATER SUPPLY SCHEME , SM/11726 | Augmentation | Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I & III and installation of grid connection solar PV system with net metering at T/W no.- I of Goalpokher Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/011422) | Assistant Engineer - I | Junior Engineer-02 | ORD/000170/2023-2024 | 2090/MLMD | 04/07/2023 | 2005 | DILIP MAHATO. | 27.26 | 17.63 | 64.67 | 65 | |
| 3 | UTTAR DINAJPUR | Raiganj Division | AUGMENTATION GOALPOKHER PIPED WATER SUPPLY SCHEME , SM/11726 | Augmentation | FHTC (Functional Household Tap Connection) for Goalpokhar Water Supply Scheme [Augmentation Scheme] in Goalpokhar-I Block of Uttar Dinajpur District Under Raiganj Division, PHE Dte. | Assistant Engineer ISD | Junior Engineer, ISD | ORD/000166/2022-2023 | 2026/RD/PHE | 17/11/2022 | 90 | MAA BICHITRA CONSTRUCTION MAABICHITRACONST@GMAIL.COM | 66.67 | 64.79 | 97.18 | 98 | |
| 4 | UTTAR DINAJPUR | Raiganj Division | AUGMENTATION GOALPOKHER PIPED WATER SUPPLY SCHEME , SM/11726 | Augmentation | Repairing for Head Work Site Pump House & Construction of Toilet at Goalpokher in connection with Goalpokher PWSS under Islampur Sub-Division under Raiganj Division,PHE Dte. | Assistant Engineer ISD | ORD/000040/2023-2024 | 1539/RD/PHE | 24/05/2023 | 45 | HAQUE CONSTRUCTION HAQUE@GMAIL.COM | 2.35 | 2.31 | 98.3 | 100 | ||
| 5 | UTTAR DINAJPUR | Malda Mechanical | AUGMENTATION GOALPOKHER PIPED WATER SUPPLY SCHEME , SM/11726 | Augmentation | W.B.S.E.D.C.LTD Quotation charge at Pole Shifting of Goalpokher PWS, Goalpokher C.C.C in the district of Uttar Dinajpur Under Malda Mechanical Division PHE Dte. | BILL/02548/2023-2024 | BP-2023-24-449 | 10/01/2024 | 0 | W.B.S.E.D.C.LTD | 1.48 | 0.00 | 0 | 0 | |||
| 6 | UTTAR DINAJPUR | Raiganj Division | AUGMENTATION GOALPOKHER PIPED WATER SUPPLY SCHEME , SM/11726 | Augmentation | Augmentation work of GOALPOKHAR and it's adjoining mouzas Piped Water Supply Scheme at Goalpokhar-I Block of Uttar Dinajpur District under Raiganj Division, P.H.E. Dte., Govt. of West Bengal. | Assistant Engineer ISD | Junior Engineer, ISD | ORD/000100/2022-2023 | 1547/RD/PHE | 26/08/2022 | 90 | AJIT PARMANIK | 319.76 | 231.47 | 72.39 | 95 | |
| 7 | UTTAR DINAJPUR | Raiganj Division | AUGMENTATION GOALPOKHER PIPED WATER SUPPLY SCHEME , SM/11726 | Augmentation | Construction of Over Head Reservoir(Capacity-500 Cum) of GOALPOKHER Pipe Water Supply Scheme in connection with Augmentation at GOALPOKHAR-I Block of Uttar Dinajpur District under Raiganj Division, P.H.E. Dte. | Assistant Engineer ISD | Junior Engineer, ISD | ORD/000380/2022-2023 | 735/RD/PHE | 15/03/2023 | 730 | HAQUE CONSTRUCTION HAQUE@GMAIL.COM | 165.64 | 54.01 | 32.61 | 85 | |
| 8 | UTTAR DINAJPUR | Raiganj Division | AUGMENTATION GOALPOKHER PIPED WATER SUPPLY SCHEME , SM/11726 | Augmentation | Repair and Maintenance of Boundary Wall and construction of Concrete Pathway at both Head work site and 2nd tube well Pump House site in connection with Augmentation of Goalpokhar Pipe W/S scheme under Islampur Sub-Division PHE Dte.under Raiganj Division, PHE Dte.,U/D. | Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD | Junior Engineer, ISD | ORD/000497/2024-2025 | 30/RD/PHE | 02/01/2025 | 45 | HAQUE CONSTRUCTION | 8.16 | 0.00 | 0 | 0 | |
| 9 | UTTAR DINAJPUR | Raiganj Division | AUGMENTATION GOALPOKHER PIPED WATER SUPPLY SCHEME , SM/11726 | Augmentation | Laying of Additional Pipeline for Retrofitting in connection with augmentation of Goalpokhar Water Supply Scheme for installation of FHTC under Islampur Sub-Division P.H.E. Dte.under Raiganj Division, P.H.E Dte.,U/D. | Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD | Junior Engineer, ISD | ORD/000499/2024-2025 | 43/RD/PHE | 03/01/2025 | 45 | HAQUE CONSTRUCTION | 40.57 | 0.00 | 0 | 0 | |
| Total | 665.86 | 370.22 | 55.6 | ||||||||||||||