Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 20,263.72 182.38 0.9  
1 COOCHBEHAR Sitai Northern Mechanical Division II BRAHMOTTAR CHATRA PIPED WATER SUPPLY SCHEME. , SM/15912 New Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Brahmottar Chatra water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/001009/2023-2024 2591/NMD-II 24/08/2023 30 M/S P.P ELECTRICALS 21.30 0.00 0 0
2 COOCHBEHAR Sitai Northern Mechanical Division II BRAHMOTTAR CHATRA PIPED WATER SUPPLY SCHEME. , SM/15912 New ELECTRIC QUOTATION BILL FOR NEW SERVICE CONNECTION AT BRAHMOTTAR CHATRA TW NO. II BILL/02615/2023-2024 BP-2023-24-578 01/02/2024 WBSEDCL 12.46 0.00 0 null
3 COOCHBEHAR Sitai Northern Mechanical Division II BRAHMOTTAR CHATRA PIPED WATER SUPPLY SCHEME. , SM/15912 New ELECTRIC QUOTATION BILL FOR NEW SERVICE CONNECTION AT BRAHMOTTAR CHATRA TW NO. I BILL/02617/2023-2024 BP-2023-24-579 01/02/2024 WBSEDCL 7.47 0.00 0 null
4 COOCHBEHAR Sitai Coochbehar Division BRAHMOTTAR CHATRA PIPED WATER SUPPLY SCHEME. , SM/15912 New Execution of different works related to BRAHMOTTAR CHATRA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1286/1-5/NBC-1; Dt.: 17-03-23 ADDITIONAL ASSISTANT ENGINEER, COOCHBEHAR DIVISION JUNIOR ENGINEER, COOCH BEHAR DIVISION,JUNIOR ENGINEER, COOCHBEHAR DIVISION ORD/000620/2022-2023 1904/CD 17/03/2023 150 AMBITIOUS ENTERPRISE 433.20 182.38 42.1 25
5 COOCHBEHAR Sitai Coochbehar Division BRAHMOTTAR CHATRA PIPED WATER SUPPLY SCHEME. , SM/15912 New Laying of DI line along both the flanks of Roads in Cooch Behar District under Cooch Behar Division PHE Dte. CONTRACTUAL ASSISTANT ENGINEER, COOCHBEHAR DIVISION JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000339/2024-2025 1264/CD 02/07/2024 300 MACKINTOSH BURN LIMITED 19,789.29 0.00 0 0
Total 20,263.72 182.38 0.9