Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
7 | 331.98 | 145.3 | 43.77 | ||||||||||||||
1 | COOCHBEHAR | Tufanganj - II | Coochbehar Division | KHAGRIBARI PIPED WATER SUPPLY SCHEME , SM/13882 | New | Execution of different works related to KHAGRIBARI PWSS under JAL JEEVAN MISSION | ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION | JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION | ORD/000343/2023-2024 | 1327/CD | 24/11/2023 | 60 | DAS ENTERPRISE | 15.07 | 0.00 | 0 | 0 |
2 | COOCHBEHAR | Tufanganj - II | Coochbehar Division | KHAGRIBARI PIPED WATER SUPPLY SCHEME , SM/13882 | New | Execution of different works related to KHAGRABARI PWSS under JAL JEEVAN MISSION | ORD/000358/2023-2024 | 1342/CD | 24/11/2023 | 60 | DAS ENTERPRISE | 1.32 | 0.00 | 0 | 0 | ||
3 | COOCHBEHAR | Tufanganj - II | Northern Mechanical Division II | KHAGRIBARI PIPED WATER SUPPLY SCHEME , SM/13882 | New | New service connection at Khagribari PWSS, P/H-I | BILL/00200/2024-2025 | BP-48/24-25 | 29/04/2024 | WBSEDCL | 4.85 | 0.00 | 0 | null | |||
4 | COOCHBEHAR | Tufanganj - II | Northern Mechanical Division II | KHAGRIBARI PIPED WATER SUPPLY SCHEME , SM/13882 | New | New service connection at Khagribari PWSS, P/H-I | BILL/00200/2024-2025 | BP-48/24-25 | 29/04/2024 | WBSEDCL | 4.85 | 0.00 | 0 | null | |||
5 | COOCHBEHAR | Tufanganj - II | Northern Mechanical Division II | KHAGRIBARI PIPED WATER SUPPLY SCHEME , SM/13882 | New | New service connection at Khagribari PWSS, P/H-II | BILL/00199/2024-2025 | BP-47/24-25 | 29/04/2024 | WBSEDCL | 3.57 | 0.00 | 0 | null | |||
6 | COOCHBEHAR | Tufanganj - II | Coochbehar Division | KHAGRIBARI PIPED WATER SUPPLY SCHEME , SM/13882 | New | Execution of different works related to KHAGRIBARI PWSS under JAL JEEVAN MISSION | ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION | JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION | ORD/000602/2023-2024 | 646/CD | 11/03/2024 | 60 | HIRAK CONSTRUCTION | 52.26 | 0.00 | 0 | 30 |
7 | COOCHBEHAR | Tufanganj - II | Coochbehar Division | KHAGRIBARI PIPED WATER SUPPLY SCHEME , SM/13882 | New | Execution of different works related to KHAGRIBARI PWSS under JAL JEEVAN MISSION | ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION | JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION | ORD/000554/2022-2023 | 1703/CD | 13/02/2023 | 150 | HIRAK CONSTRUCTION | 250.06 | 145.30 | 58.11 | 90 |
Total | 331.98 | 145.30 | 43.77 |