Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 357.22 188.58 52.79  
1 COOCHBEHAR Dinhata - I Coochbehar Division DAKHSHIN DIGHALTARI PWSS , SM/13388 New Execution of different works related to DAKHSHIN DIGHALTARI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1122/1-5/NBC-1; Dt.: 13-02-23 ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION,ASSISTANT ENGINEER, HEAD QUARTER,COOCHBEHAR DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION,JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION ORD/000603/2022-2023 1855/CD 14/03/2023 150 SANKAR CHAKRABORTY 303.42 188.58 62.15 54
2 COOCHBEHAR Dinhata - I Coochbehar Division DAKHSHIN DIGHALTARI PWSS , SM/13388 New Execution of different works related to DAKSHIN DIGHALTARI PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000422/2023-2024 1478/CD 20/12/2023 60 SANKAR CHAKRABORTY 53.80 0.00 0 90
Total 357.21 188.58 52.79