Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 205.14 5.44 2.65  
1 COOCHBEHAR Haldibari Northern Mechanical Division II Ground Water Based Piped Water Supply Scheme DEBOTTAR BAKSHIGANJ (BLOCK-HALDIBARI) , SM/13287 New QUOTATION FOR NEW SERVICE CONNECTION AT DEBOTTAR BOXIGANJ TW NO-I BILL/00087/2023-2024 BP-2023-24-75 15/05/2023 WBSEDCL 0.93 0.00 0 0
2 COOCHBEHAR Haldibari Northern Mechanical Division II Ground Water Based Piped Water Supply Scheme DEBOTTAR BAKSHIGANJ (BLOCK-HALDIBARI) , SM/13287 New Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Debottar Bakshiganj Water Supply Scheme TW No.- I under NMD-II,PHE.Dte,Apd. Assistant Engineer, Cooch-Behar Mechanical Sub-Division Junior Engineer 4, Cooch-Behar Mechanical Sub-Division, ORD/000667/2023-2024 2024/NMD-II 26/07/2023 30 TAPAN BISWAS 10.46 0.00 0 0
3 COOCHBEHAR Haldibari Coochbehar Division Ground Water Based Piped Water Supply Scheme DEBOTTAR BAKSHIGANJ (BLOCK-HALDIBARI) , SM/13287 New Execution of different works related to DEBOTTAR BAKSHIGANJ PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, MATHABHANGA SUB-DIVISION JUNIOR ENGINEER, MATHABHANGA SUB-DIVISION,JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION,JUNIOR ENGINEER, RWS COOCHBEHAR SUB-DIVISION,JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000555/2022-2023 1702/CD 13/02/2023 150 DAS ENTERPRISE 120.12 0.00 0 30
4 COOCHBEHAR Haldibari Coochbehar Division Ground Water Based Piped Water Supply Scheme DEBOTTAR BAKSHIGANJ (BLOCK-HALDIBARI) , SM/13287 New FHTC AT SITALKUCHI PWSS Z-III BILL/01044/2023-2024 BP-500 22/09/2023 Z STAR COMMOTRADE PVT LTD 28.95 0.00 0 0
5 COOCHBEHAR Haldibari Coochbehar Division Ground Water Based Piped Water Supply Scheme DEBOTTAR BAKSHIGANJ (BLOCK-HALDIBARI) , SM/13287 New EXECUTION OF MDIFFERENT WORKS AT DEBOTTAR BAKSHIGANJ PWSS BILL/01107/2023-2024 BP-546 07/10/2023 DAS ENTERPRISE 35.11 0.00 0 0
6 COOCHBEHAR Haldibari Coochbehar Division Ground Water Based Piped Water Supply Scheme DEBOTTAR BAKSHIGANJ (BLOCK-HALDIBARI) , SM/13287 New Execution of different works related to DEBOTTAR BAKSHIGANJ PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, MATHABHANGA SUB-DIVISION JUNIOR ENGINEER, RWS COOCHBEHAR SUB-DIVISION ORD/000442/2022-2023 1419/CD 29/12/2022 30 NARESH CH.MANDAL 9.57 5.44 56.84 30
Total 205.13 5.44 2.65